Proposal to Improve the Operational Availability of the Canning Machine in a Craft Brewery through the Application of Work Study, SMED, and Planned Maintenance

Open source

1Bibliographic record

Authors
Evelin Josefina Suarez Montes, Maria Grazia Ximena Ascaño Arce
Year
2026
Venue
Repositorio Académico UPC (Universidad Peruana de Ciencias Aplicadas)
DOI
—
Country
Peru
Segment
Brewing, wine and spirits
Process family
Filling and packaging line
Study type
Before/after intervention
Extraction scope
Full text
Size
1 plants · — lines · 1 machines
Observation period
120 days
Data collection
not_reported
Intervention
Show the setting as described by the study
The objective of this study was to increase the operational availability of the canning machine in a craft brewery, as it exhibited an average availability of 78%, which was below the target standard of 85%, thereby affecting the continuity of the packaging process and the company's profitability.

2Risk of bias

Scored with the rubric of the protocol: 2 low concern, 1 some concerns, 0 high concern.
Total score 7High risk
ItemScore
Is the observed line, machine or plant described well enough to classify its segment, process and equipment?Product or sector is given but the equipment or process is only partly described.1 / 2
Is the observation period long enough and reported?Period reported and at least 30 days of production (or at least 100 recorded events).2 / 2
How were loss data collected?Interviews, estimates, or method not reported.0 / 2
Are OEE, loading time and the loss categories defined explicitly?No definition; metrics are reported as bare numbers.0 / 2
Does the loss breakdown account for the total loss it claims to explain?Only selected causes are reported and the total is unknown.0 / 2
Is there evidence of selective reporting of favourable results?Intervention study in which baseline and post-intervention periods differ in length or method.1 / 2
Are the reported numbers internally consistent?Small inconsistencies (2 to 10 percentage points) or values that cannot be cross-checked.1 / 2
Could conflicts of interest or the source of the data bias the result?Academic or independent study, or conflicts declared and unrelated to the result.2 / 2

3Extracted data

Each datum with its classification and the verbatim quote that states it.
Reported causeLoss categoryMetricValueExtraction
electrical failurecanning machine
Show verbatim quote (Abstract)
Furthermore, the mechanical MTBF increased from 98.74 h to 117.25 h, while the electrical MTBF increased from 144.31 h to 170.55 h.
Equipment failure (breakdowns)Time between events171 hBoth extractors agreed
mechanical failurecanning machine
Show verbatim quote (Abstract)
Furthermore, the mechanical MTBF increased from 98.74 h to 117.25 h, while the electrical MTBF increased from 144.31 h to 170.55 h.
Equipment failure (breakdowns)Time between events117 hBoth extractors agreed
electrical failurecanning machine
Show verbatim quote (Abstract)
the electrical MTTR decreased from 7.20 h to 5.17 h
Equipment failure (breakdowns)Mean event duration5.17 hBoth extractors agreed
mechanical failurecanning machine
Show verbatim quote (Abstract)
the mechanical MTTR decreased from 9.73 h to 7.50 h
Equipment failure (breakdowns)Mean event duration7.50 hBoth extractors agreed
preventive maintenancecanning machine
Show verbatim quote (Abstract)
the preventive maintenance MTTR decreased from 3.38 h to 2.38 h
Planned downtime (scheduled maintenance, breaks, no demand)Mean event duration2.38 hBoth extractors agreed
—canning machine
Show verbatim quote (Abstract)
Operational availability increased from 78% to 82.75%, the preventive maintenance MTTR decreased from 3.38 h to 2.38 h, the average setup time was reduced from 7.25 h to 5.50 h, the mechanical MTTR decreased from 9.73 h to 7.50 h, and the electrical MTTR decreased from 7.20 h to 5.17 h.
noneAvailability82.8 %Both extractors agreed
electrical failurecanning machine
Show verbatim quote (Abstract)
Furthermore, the mechanical MTBF increased from 98.74 h to 117.25 h, while the electrical MTBF increased from 144.31 h to 170.55 h.
Equipment failure (breakdowns)Time between events144 hBoth extractors agreed
mechanical failurecanning machine
Show verbatim quote (Abstract)
Furthermore, the mechanical MTBF increased from 98.74 h to 117.25 h, while the electrical MTBF increased from 144.31 h to 170.55 h.
Equipment failure (breakdowns)Time between events98.7 hBoth extractors agreed
electrical failurecanning machine
Show verbatim quote (Abstract)
the electrical MTTR decreased from 7.20 h to 5.17 h
Equipment failure (breakdowns)Mean event duration7.20 hBoth extractors agreed
mechanical failurecanning machine
Show verbatim quote (Abstract)
the mechanical MTTR decreased from 9.73 h to 7.50 h
Equipment failure (breakdowns)Mean event duration9.73 hBoth extractors agreed
preventive maintenancecanning machine
Show verbatim quote (Abstract)
the preventive maintenance MTTR decreased from 3.38 h to 2.38 h
Planned downtime (scheduled maintenance, breaks, no demand)Mean event duration3.38 hBoth extractors agreed
—canning machine
Show verbatim quote (Abstract)
Operational availability increased from 78% to 82.75%, the preventive maintenance MTTR decreased from 3.38 h to 2.38 h, the average setup time was reduced from 7.25 h to 5.50 h, the mechanical MTTR decreased from 9.73 h to 7.50 h, and the electrical MTTR decreased from 7.20 h to 5.17 h.
noneAvailability78.0 %Both extractors agreed
setupcanning machine
Show verbatim quote (Abstract)
the average setup time was reduced from 7.25 h to 5.50 h
Setup and adjustmentsMean event duration5.50 hBoth extractors agreed
setupcanning machine
Show verbatim quote (Abstract)
the average setup time was reduced from 7.25 h to 5.50 h
Setup and adjustmentsMean event duration7.25 hBoth extractors agreed

Observation units

  • Canning machine · Filling · After intervention
  • Canning machine · Filling · Baseline