Changeover and setup adjustment on grinding mill
In short
It appears in about 1 of every 100 lines studied.
When it appears, it takes on average about 54 % of the line's lost time. Reported by 2 of the 43 studies that could observe it (limited evidence).
What happens
Production stops while the grinding mill is reconfigured between runs: changing grinding plates, screens or rollers, resetting gaps and feed parameters, and fine-tuning the machine until it reaches stable operating conditions for the new product or specification. This elapsed time between the last good unit of the previous run and the first good unit of the next run is non-productive by nature.
What is done about it
Standardize and document the setup procedure with pre-set gap and feed references per product, use quick-change tooling for plates/screens, and prepare parts and adjustments offline (SMED approach) to shorten the changeover window.
Practical guidance written from engineering knowledge; it is not a statistical estimate.
1Probability and evidence
- Probability of presence
- 1.3% [0.2–3.7%]
- Expected share of lost time
- 0.7% [0.1–1.9%]
- Share of lost time when present
- 54% [42–64%]
- Studies / units
- 43 / 48
- Evidence grade
- C
Grade C: 2 to 4 studies, or an interval wider than 0.35.
2Probability by segment
- Dairy products1.4% [0.1–5.3%]5 studies
- Soft drinks, bottled water and juices1.5% [0.1–5.9%]1 study
- Brewing, wine and spirits1.5% [0.1–6.0%]0 studies
- Bakery and pasta1.5% [0.1–5.6%]0 studies
- Meat, poultry and seafood1.5% [0.2–6.0%]0 studies
- Fruit and vegetable processing1.4% [0.2–5.3%]2 studies
- Grain and oilseed milling1.4% [0.1–5.5%]7 studies
- Sugar and confectionery1.9% [0.2–6.3%]10 studies
- Snacks, coffee, tea and other foods1.3% [0.1–4.9%]5 studies
- Animal feed and pet food2.0% [0.2–7.4%]6 studies
- Food manufacturing (unspecified or mixed)1.4% [0.2–5.1%]7 studies
3Mechanism, SCADA signature and countermeasure
Mechanism
Engineering guidanceProduction stops while the grinding mill is reconfigured between runs: changing grinding plates, screens or rollers, resetting gaps and feed parameters, and fine-tuning the machine until it reaches stable operating conditions for the new product or specification. This elapsed time between the last good unit of the previous run and the first good unit of the next run is non-productive by nature.
How it looks in SCADA data
Engineering guidanceSCADA/MES shows the mill in a changeover or setup machine-state with the line otherwise idle or starved downstream, bracketed by order or recipe change events; motor running at low or no load with no material throughput logged, followed by a ramp-up period before stable speed and load are reached.
Countermeasure
Engineering guidanceStandardize and document the setup procedure with pre-set gap and feed references per product, use quick-change tooling for plates/screens, and prepare parts and adjustments offline (SMED approach) to shorten the changeover window.
4Sources
- USULAN PENINGKATAN EFEKTIVITAS MESIN CETAK MANUAL MENGGUNAKAN METODE OVERALL EQUIPMENT EFFECTIVENESS (OEE) (STUDI KASUS DI PERUSAHAAN KERUPUK TTN) (2014)Open sourceShare of planned time: 7.35 % · as reported: “Setup and Adjustment Losses”
Show verbatim quote
= 750 10200 𝑥 100% = 7,353
- ANALISIS PRODUKTIVITAS MESIN PRESS DENGAN PENDEKATAN OVERALL EQUIPMENT EFFECTIVENESS(OEE) PADAPT. JAPFA COMFEED INDONESIA LAMPUNG (2017)Open sourceShare of lost time: 1.82 % · as reported: “Setup and adjusment losses”
Show verbatim quote
Setup and adjusment losses 6,00 1,82 99,21
- ANALISIS PRODUKTIVITAS MESIN PRESS DENGAN PENDEKATAN OVERALL EQUIPMENT EFFECTIVENESS(OEE) PADAPT. JAPFA COMFEED INDONESIA LAMPUNG (2017)Open sourceLost time: 6.00 jam · as reported: “Setup and adjusment losses”
Show verbatim quote
Setup and adjusment losses 6,00 1,82 99,21
- Share of lost time: 0.159 % · as reported: “setup and adjustment losses”
Show verbatim quote
Rata-rata kerugian yang terjadi pada setiap mesin yaitu breakdown losses 0,048%, setup and adjustment losses 0,159%, idle and minor stoppages 12,127%, dan reduced speed losses 11,749%.
- Peningkatan overall equipment effectiveness (OEE) mesin grinding pada produksi cokelat bubuk di PT ABC (2023)Open sourceShare of planned time: 4.00 % · as reported: “set up and adjustment”
Show verbatim quote
Rata-rata waktu set up & adjustment losses pada mesin grinding yaitu sebesar 4%.
- Peningkatan overall equipment effectiveness (OEE) mesin grinding pada produksi cokelat bubuk di PT ABC (2023)Open sourceLost time: 22.0 jam · as reported: “setup and adjustment”
Show verbatim quote
Setup and adjustment (jam) 22 35 12 18 42 17
- Peningkatan overall equipment effectiveness (OEE) mesin grinding pada produksi cokelat bubuk di PT ABC (2023)Open sourceLost time: 35.0 jam · as reported: “setup and adjustment”
Show verbatim quote
Setup and adjustment (jam) 22 35 12 18 42 17
- Peningkatan overall equipment effectiveness (OEE) mesin grinding pada produksi cokelat bubuk di PT ABC (2023)Open sourceLost time: 12.0 jam · as reported: “setup and adjustment”
Show verbatim quote
Setup and adjustment (jam) 22 35 12 18 42 17
- Peningkatan overall equipment effectiveness (OEE) mesin grinding pada produksi cokelat bubuk di PT ABC (2023)Open sourceLost time: 18.0 jam · as reported: “setup and adjustment”
Show verbatim quote
Setup and adjustment (jam) 22 35 12 18 42 17
- Peningkatan overall equipment effectiveness (OEE) mesin grinding pada produksi cokelat bubuk di PT ABC (2023)Open sourceLost time: 42.0 jam · as reported: “setup and adjustment”
Show verbatim quote
Setup and adjustment (jam) 22 35 12 18 42 17
- Peningkatan overall equipment effectiveness (OEE) mesin grinding pada produksi cokelat bubuk di PT ABC (2023)Open sourceLost time: 17.0 jam · as reported: “setup and adjustment”
Show verbatim quote
Setup and adjustment (jam) 22 35 12 18 42 17
- Implementing Lean and TPM for Machine Availability Enhancement: A Case Study in the Peruvian Food Processing Industry (2025)Open sourceLost time: 210 minute · as reported: “setup time (total)”
Show verbatim quote
Time to set up minute 303.54 195 210.02 -30.81%
- Implementing Lean and TPM for Machine Availability Enhancement: A Case Study in the Peruvian Food Processing Industry (2025)Open sourceLost time: 304 minute · as reported: “setup time (total)”
Show verbatim quote
Time to set up minute 303.54 195 210.02 -30.81%
- Implementing Lean and TPM for Machine Availability Enhancement: A Case Study in the Peruvian Food Processing Industry (2025)Open sourceNumber of events: 175 times · as reported: “faults”
Show verbatim quote
Number of faults times 243 120 175 -27.98%
- Implementing Lean and TPM for Machine Availability Enhancement: A Case Study in the Peruvian Food Processing Industry (2025)Open sourceNumber of events: 243 times · as reported: “faults”
Show verbatim quote
Number of faults times 243 120 175 -27.98%
- Implementing Lean and TPM for Machine Availability Enhancement: A Case Study in the Peruvian Food Processing Industry (2025)Open sourceLost time: 301 minutes · as reported: “setup time (total)”
Show verbatim quote
As a result, the total setup time decreased from 301.28 minutes to 210.02 minutes, representing a 30.81% improvement.
- Implementing Lean and TPM for Machine Availability Enhancement: A Case Study in the Peruvian Food Processing Industry (2025)Open sourceLost time: 301 minutes · as reported: “internal setup activities”
Show verbatim quote
The total time for internal activities was reduced from 301.28 minutes to 225.21 minutes, representing a 25.63% reduction in downtime, while external tasks remained stable or were improved slightly.
- Implementing Lean and TPM for Machine Availability Enhancement: A Case Study in the Peruvian Food Processing Industry (2025)Open sourceShare of lost time: 25.0 % · as reported: “frequent operator failures”
Show verbatim quote
At Level 1 of the analysis, the primary causes were identified as high unproductive times (75%) and frequent operator failures (25%).
- Implementing Lean and TPM for Machine Availability Enhancement: A Case Study in the Peruvian Food Processing Industry (2025)Open sourceShare of lost time: 29.0 % · as reported: “frequent setup stops”
Show verbatim quote
At Level 2, the root causes of unproductive times were mainly attributed to high machine shutdowns due to failure (45.98%) and frequent setup stops (29.02%).
- Implementing Lean and TPM for Machine Availability Enhancement: A Case Study in the Peruvian Food Processing Industry (2025)Open sourceLost time: 225 minutes · as reported: “internal setup activities”
Show verbatim quote
The total time for internal activities was reduced from 301.28 minutes to 225.21 minutes, representing a 25.63% reduction in downtime, while external tasks remained stable or were improved slightly.
- ANALISIS EFEKTIVITAS MESIN POLES BERAS (RICE POLISHER) MENGGUNAKAN METODE OVERALL EQUIPMENT EFFECTIVENESS (OEE) DAN SIX BIG LOSSES PADA PB TRI HANIFA BERBASIS KONSEP TOTAL PRODUCTIVE MAINTENANCE (TPM) (2026)Open sourceShare of lost time: 0.730 % · as reported: “setup & adjustment losses”
Show verbatim quote
Sementara itu, breakdown losses sebesar 3,33%, setup & adjustment losses sebesar 0,73%, dan process defect losses sebesar 2,5% tergolong rendah, sehingga tidak menjadi faktor dominan dalam penurunan kinerja mesin.