Mitigating solids loss and waste in processed cheese production

Open source

1Bibliographic record

Authors
Daniel M. Sterckx
Year
2020
Venue
Minds at UW (University of Wisconsin)
DOI
—
Country
United States
Segment
Dairy products
Process family
Filling and packaging line
Study type
Before/after intervention
Extraction scope
Full text
Size
1 plants · 1 lines · — machines
Observation period
84 days
Data collection
manual_logs
Intervention
Show the setting as described by the study
At one domestic plant, Plant A, the natural shred line ran from 28 to 30 million pounds per year, whereas the processed lines ran in excess of 135 million pounds per year.

2Risk of bias

Scored with the rubric of the protocol: 2 low concern, 1 some concerns, 0 high concern.
Total score 9Moderate risk
ItemScore
Is the observed line, machine or plant described well enough to classify its segment, process and equipment?Product, process and equipment are all described.2 / 2
Is the observation period long enough and reported?Period reported and at least 30 days of production (or at least 100 recorded events).2 / 2
How were loss data collected?Manual logs or maintenance records with unknown completeness.1 / 2
Are OEE, loading time and the loss categories defined explicitly?A standard definition is cited but its application is not shown.1 / 2
Does the loss breakdown account for the total loss it claims to explain?Only selected causes are reported and the total is unknown.0 / 2
Is there evidence of selective reporting of favourable results?Intervention study in which baseline and post-intervention periods differ in length or method.1 / 2
Are the reported numbers internally consistent?Small inconsistencies (2 to 10 percentage points) or values that cannot be cross-checked.1 / 2
Could conflicts of interest or the source of the data bias the result?Authors are employees of the plant or of an equipment/software vendor; no declaration.1 / 2

3Extracted data

Each datum with its classification and the verbatim quote that states it.
Reported causeLoss categoryMetricValueExtraction
wrapper error wastewrapper
Show verbatim quote (Chapter IV, Addressing Equipment Error)
Prior to the start of the project, an average of 148,900 pounds of cheese salvage was created weekly as a result of wrapper error waste. This translated into a 10.24% salvage rate.
Process defects (scrap and rework)Defect rate10.2 %Adjudicated
Equipment Failures
Show verbatim quote (Table 1)
590 Equipment Failures
Equipment failure (breakdowns)Lost time590 minSingle extractor
Pump Replacementspump
Show verbatim quote (Table 1)
411 Pump Replacements
Equipment failure (breakdowns)Lost time411 minSingle extractor
Lecithin Issues
Show verbatim quote (Table 1)
235 Lecithin Issues
Organizational or external stops (material or personnel shortage, utilities outage)Lost time235 minSingle extractor
late startups
Show verbatim quote (Chapter IV, Addressing Human Error)
Upon initial review, production was late on average 31 minutes per week over the 26-week period.
Setup and adjustmentsLost time31.0 min/weekSingle extractor
lost production time (late start-ups and work stoppages)
Show verbatim quote (Chapter V, Addressing human waste)
For a 26-week period prior to starting the project, a cumulative 14 hours of lost production time was observed.
Not classifiable from the reportLost time14.0 hSingle extractor
—line_unspecified
Show verbatim quote (Chapter V, Addressing human waste)
For every hour the line was down, 20,000 pounds of cheese production was lost.
noneThroughput20,000 lbs/hSingle extractor
bottom seal/end seal issueswrapper
Show verbatim quote (Chapter V, page 41)
Since centerlining the wrappers and running at ideal settings, at the close of the project, Company XYZ was running at 120,900 pounds of salvage per week.
Process defects (scrap and rework)Defect rate120,900 lbs/weekSingle extractor
Blender scrape down processblender
Show verbatim quote (Chapter V, page 42)
This (on average) prevented 2,000 pounds of cheese being diverted to solids recovery tanks per week.
Organizational or external stops (material or personnel shortage, utilities outage)Lost time2,000 lbsSingle extractor

Observation units

  • Processed Cheese Casting Line (Plant A) · Whole line or unspecified equipment · Baseline
  • Processed Cheese Production Line · Whole line or unspecified equipment · After intervention