Integrating SMED and Mechanical Design for Changeover Reduction in Beverage Packaging Lines

Open source

1Bibliographic record

Authors
António Rocha Esteves
Year
2026
Venue
Portuguese National Funding Agency for Science, Research and Technology (RCAAP Project by FCT)
DOI
—
Country
Portugal
Segment
Brewing, wine and spirits
Process family
Filling and packaging line
Study type
Before/after intervention
Extraction scope
Full text
Size
1 plants · 4 lines · 2 machines
Observation period
731 days
Data collection
manual_logs
Intervention
Show the setting as described by the study
This dissertation, developed at the Super Bock Group's plant in Leça do Balio, addresses these losses on the Kisters and Mead secondary-packaging machines by combining the Single-Minute Exchange of Die (SMED) methodology with formal machine design

2Risk of bias

Scored with the rubric of the protocol: 2 low concern, 1 some concerns, 0 high concern.
Total score 12Moderate risk
ItemScore
Is the observed line, machine or plant described well enough to classify its segment, process and equipment?Product, process and equipment are all described.2 / 2
Is the observation period long enough and reported?Period reported and at least 30 days of production (or at least 100 recorded events).2 / 2
How were loss data collected?Manual logs or maintenance records with unknown completeness.1 / 2
Are OEE, loading time and the loss categories defined explicitly?A standard definition is cited but its application is not shown.1 / 2
Does the loss breakdown account for the total loss it claims to explain?The reported causes or categories sum to at least 90% of the stated total, or an explicit "other" class closes the balance.2 / 2
Is there evidence of selective reporting of favourable results?Intervention study in which baseline and post-intervention periods differ in length or method.1 / 2
Are the reported numbers internally consistent?Recomputed totals, shares and OEE factors agree with the reported values within 2 percentage points.2 / 2
Could conflicts of interest or the source of the data bias the result?Authors are employees of the plant or of an equipment/software vendor; no declaration.1 / 2

3Extracted data

Each datum with its classification and the verbatim quote that states it.
Reported causeLoss categoryMetricValueExtraction
—
Show verbatim quote (Section 1.1, Figure 1.2)
during 2025 production (annual OEE averaged 61.63%)
noneOEE61.6 %Both extractors agreed
—
Show verbatim quote (Section 1.1, Figure 1.1)
with an overall average of 58.8% (Figure 1.1)
noneOEE58.8 %Both extractors agreed
proactive retrieval of Format PartsKisters
Show verbatim quote (Table 6.2)
Line 6 8 1.0/1.5 0.0 1.0/1.5
Setup and adjustmentsLost time0 minBoth extractors agreed
Breakdowns and Malfunctions Time (BMT)
Show verbatim quote (Section 1.2)
Although breakdown and malfunction losses (18.04%) are greater in aggregate than changeover and ramp-up losses (≈7.2%), they are not the focus of this study.
Equipment failure (breakdowns)Share of planned time18.0 %Single extractor
Changeover Time (COT) and Ramp-Up Time (RUT)
Show verbatim quote (Section 1.2)
Although breakdown and malfunction losses (18.04%) are greater in aggregate than changeover and ramp-up losses (≈7.2%), they are not the focus of this study.
Setup and adjustmentsShare of planned time7.20 %Single extractor
proactive retrieval of Format PartsKisters
Show verbatim quote (Table 6.2)
Line 1 6 0.5 0.0 0.5
Setup and adjustmentsLost time0.500 minSingle extractor
proactive retrieval of Format PartsKisters
Show verbatim quote (Table 6.2)
Line 1 6 0.5 0.0 0.5
Setup and adjustmentsLost time0 minSingle extractor
proactive retrieval of Format PartsKisters
Show verbatim quote (Table 6.2)
Line 2 6 1.0 0.0 1.0
Setup and adjustmentsLost time1.00 minSingle extractor
proactive retrieval of Format PartsKisters
Show verbatim quote (Table 6.2)
Line 2 6 1.0 0.0 1.0
Setup and adjustmentsLost time0 minSingle extractor
proactive retrieval of Format PartsKisters
Show verbatim quote (Table 6.2)
Line 5 10 1.0 0.0 1.0
Setup and adjustmentsLost time1.00 minSingle extractor
proactive retrieval of Format PartsKisters
Show verbatim quote (Table 6.2)
Line 5 10 1.0 0.0 1.0
Setup and adjustmentsLost time0 minSingle extractor
proactive retrieval of Format PartsKisters
Show verbatim quote (Table 6.2)
Line 6 8 1.0/1.5 0.0 1.0/1.5
Setup and adjustmentsLost time1.00 minSingle extractor
Type A changeoverKisters
Show verbatim quote (Table 6.4)
Type A 30.0, 33.0 (µ = 31.5) 24.0, 26.0 (µ = 25.0) 6.5 min 20.6%
Setup and adjustmentsMean event duration31.5 minSingle extractor
Type B changeoverKisters
Show verbatim quote (Table 6.4)
Type B 35.0, 28.0 (µ = 31.5) 26.0, 27.0 (µ = 26.5) 5.0 min 15.9%
Setup and adjustmentsMean event duration31.5 minSingle extractor
Type C changeoverKisters
Show verbatim quote (Table 6.4)
Type C 38.0, 49.0 (µ = 43.5) 35.0, 37.0 (µ = 37.5) 6.0 min 13.8%
Setup and adjustmentsMean event duration43.5 minSingle extractor
Type D changeoverKisters
Show verbatim quote (Table 6.4)
Type D 39.0, 39.0, 48.0 (µ = 42.0) 35.0, 35.0 (µ = 35.0) 7.0 min 16.7%
Setup and adjustmentsMean event duration42.0 minSingle extractor
pooled all changeover types (A, B, C, D)Kisters
Show verbatim quote (Section 6.4.2)
The pooled analysis shows a mean reduction from 37.7 to 30.6 minutes (18.7%), with a large effect size (Hedges’ g = 1.04).
Setup and adjustmentsMean event duration37.7 minSingle extractor
Type A changeoverKisters
Show verbatim quote (Table 6.4)
Type A 30.0, 33.0 (µ = 31.5) 24.0, 26.0 (µ = 25.0) 6.5 min 20.6%
Setup and adjustmentsMean event duration25.0 minSingle extractor
Type B changeoverKisters
Show verbatim quote (Table 6.4)
Type B 35.0, 28.0 (µ = 31.5) 26.0, 27.0 (µ = 26.5) 5.0 min 15.9%
Setup and adjustmentsMean event duration26.5 minSingle extractor
Type C changeoverKisters
Show verbatim quote (Table 6.4)
Type C 38.0, 49.0 (µ = 43.5) 35.0, 37.0 (µ = 37.5) 6.0 min 13.8%
Setup and adjustmentsMean event duration37.5 minSingle extractor
Type D changeoverKisters
Show verbatim quote (Table 6.4)
Type D 39.0, 39.0, 48.0 (µ = 42.0) 35.0, 35.0 (µ = 35.0) 7.0 min 16.7%
Setup and adjustmentsMean event duration35.0 minSingle extractor
pooled all changeover types (A, B, C, D)Kisters
Show verbatim quote (Section 6.4.2)
The pooled analysis shows a mean reduction from 37.7 to 30.6 minutes (18.7%), with a large effect size (Hedges’ g = 1.04).
Setup and adjustmentsMean event duration30.6 minSingle extractor
Cardboard Module tuning stoppagesCardboard Cutout Feeding Module
Show verbatim quote (Section 7.2, Figure 7.3)
Among the 29 changeovers interrupted for these reasons, 24 experienced multiple stoppages.
Setup and adjustmentsNumber of events29.0 changeoversSingle extractor
Cardboard Module tuning stoppages (multiple stoppages)Cardboard Cutout Feeding Module
Show verbatim quote (Section 7.2, Figure 7.3)
Among the 29 changeovers interrupted for these reasons, 24 experienced multiple stoppages.
Setup and adjustmentsNumber of events24.0 changeoversSingle extractor
Cardboard Module fine-tuning (single stoppage)Cardboard Cutout Feeding Module
Show verbatim quote (Section 7.2, Figure 7.4)
The median fine-tuning duration is 6 minutes for changeovers with a single stoppage, rising to 14 minutes for changeovers with two or more stoppages.
Setup and adjustmentsMean event duration6.00 minSingle extractor
Cardboard Module fine-tuning (two or more stoppages)Cardboard Cutout Feeding Module
Show verbatim quote (Section 7.2, Figure 7.4)
The median fine-tuning duration is 6 minutes for changeovers with a single stoppage, rising to 14 minutes for changeovers with two or more stoppages.
Setup and adjustmentsMean event duration14.0 minSingle extractor
Folding Bracket Assembly Task (Redesigned Component)Kisters Folding Bracket Module
Show verbatim quote (Abstract, page ii)
A redesigned tool-less folding bracket reduced its adjustment task time by 78.5% and its variance by 99.3% under statistically conclusive testing.
Setup and adjustmentsMean event duration78.5 % reductionSingle extractor

Observation units

  • Lines 1, 2, 5 and 6 (whole plant, SBG Leça do Balio) · Whole line or unspecified equipment · Baseline
  • Kisters - Line 6 (Format Parts Retrieval task) · Packaging (forming, sealing, wrapping, case packing, palletizing) · After intervention
  • Kisters - Line 1 (Format Parts Retrieval task) · Packaging (forming, sealing, wrapping, case packing, palletizing) · Baseline
  • Kisters - Line 1 (Format Parts Retrieval task) · Packaging (forming, sealing, wrapping, case packing, palletizing) · After intervention
  • Kisters - Line 2 (Format Parts Retrieval task) · Packaging (forming, sealing, wrapping, case packing, palletizing) · Baseline
  • Kisters - Line 2 (Format Parts Retrieval task) · Packaging (forming, sealing, wrapping, case packing, palletizing) · After intervention
  • Kisters - Line 5 (Format Parts Retrieval task) · Packaging (forming, sealing, wrapping, case packing, palletizing) · Baseline
  • Kisters - Line 5 (Format Parts Retrieval task) · Packaging (forming, sealing, wrapping, case packing, palletizing) · After intervention
  • Kisters - Line 6 (Format Parts Retrieval task) · Packaging (forming, sealing, wrapping, case packing, palletizing) · Baseline
  • Kisters - Line 1 (Adjustment Values / Slider Optimisation) · Packaging (forming, sealing, wrapping, case packing, palletizing) · Baseline
  • Kisters - Line 1 (Adjustment Values / Slider Optimisation) · Packaging (forming, sealing, wrapping, case packing, palletizing) · After intervention
  • Kisters - Cardboard Cutout Feeding Module (observed changeovers, Feb-May 2026, all lines) · Packaging (forming, sealing, wrapping, case packing, palletizing) · Baseline
  • Line 1 Kisters · Packaging (forming, sealing, wrapping, case packing, palletizing) · After intervention