Labeling machine equipment failure
In short
It appears in about 2 of every 100 lines studied.
When it appears, it takes on average about 58 % of the line's lost time. Reported by 8 of the 85 studies that could observe it (good evidence).
What happens
A mechanical, electrical, pneumatic or sensor component of the labeling station degrades or breaks (label dispensing head, reel drive, glue/print unit, photocell, applicator pad, or container-guide alignment), so the machine can no longer apply, align or print labels correctly and stops or runs with defects until a technician intervenes. The same failure mode also produces secondary effects such as label jams, misalignment, wasted labels and container tailback on the infeed conveyor.
What is done about it
Implement condition-based and preventive maintenance on dispensing heads, drive belts, sensors and applicator components, with spare-part kits available to shorten repair time. Standardize fault diagnostics and operator response procedures, and track recurring fault codes to drive root-cause corrective actions and design improvements.
Practical guidance written from engineering knowledge; it is not a statistical estimate.
1Probability and evidence
- Probability of presence
- 2.0% [0.6–4.7%]
- Expected share of lost time
- 1.2% [0.4–2.8%]
- Share of lost time when present
- 58% [49–67%]
- Studies / units
- 85 / 113
- Evidence grade
- B
Grade B: 5 to 9 studies, or an interval width between 0.20 and 0.35.
2Probability by segment
- Dairy products2.0% [0.3–6.1%]11 studies
- Soft drinks, bottled water and juices6.8% [2.3–14.1%]29 studies
- Brewing, wine and spirits2.0% [0.3–5.7%]13 studies
- Bakery and pasta2.4% [0.3–7.9%]1 study
- Meat, poultry and seafood2.2% [0.3–6.9%]4 studies
- Fruit and vegetable processing2.3% [0.3–7.3%]4 studies
- Grain and oilseed milling2.3% [0.3–7.4%]3 studies
- Sugar and confectionery2.2% [0.3–7.4%]3 studies
- Snacks, coffee, tea and other foods2.2% [0.3–6.8%]4 studies
- Animal feed and pet food2.3% [0.3–7.3%]4 studies
- Food manufacturing (unspecified or mixed)2.2% [0.3–6.7%]9 studies
3Mechanism, SCADA signature and countermeasure
Mechanism
Engineering guidanceA mechanical, electrical, pneumatic or sensor component of the labeling station degrades or breaks (label dispensing head, reel drive, glue/print unit, photocell, applicator pad, or container-guide alignment), so the machine can no longer apply, align or print labels correctly and stops or runs with defects until a technician intervenes. The same failure mode also produces secondary effects such as label jams, misalignment, wasted labels and container tailback on the infeed conveyor.
How it looks in SCADA data
Engineering guidanceSCADA/MES logs show the labeler state changing to fault or stopped with equipment-related alarm codes (dispensing error, print head error, photocell fault, servo/drive fault), accompanied by rising stop counters and maintenance work-order flags. Upstream or downstream machine states often shift to blocked or starved while the labeler is down, and label-waste or reject counters increase around the fault events.
Countermeasure
Engineering guidanceImplement condition-based and preventive maintenance on dispensing heads, drive belts, sensors and applicator components, with spare-part kits available to shorten repair time. Standardize fault diagnostics and operator response procedures, and track recurring fault codes to drive root-cause corrective actions and design improvements.
4Sources
- Number of events: 10.0 events · as reported: “Yazıcı”
Show verbatim quote
YAZICI | Yazıcı | 10
- Number of events: 9.00 events · as reported: “Yazıcı”
Show verbatim quote
YAZICI | Yazıcı | 9
- Failure data analysis for preventive maintenance scheduling of a bottling company production system (2021)Open sourceNumber of events: 40.0 events · as reported: “Lb”
Show verbatim quote
Lb Lv Lc La Others Lf Lg 0 10 20 30 40 50 60 70 80 90 20% 40% 60% 80% 100% 40 17 12 8 6 2 1
- Failure data analysis for preventive maintenance scheduling of a bottling company production system (2021)Open sourceNumber of events: 17.0 events · as reported: “Lv”
Show verbatim quote
Lb Lv Lc La Others Lf Lg 0 10 20 30 40 50 60 70 80 90 20% 40% 60% 80% 100% 40 17 12 8 6 2 1
- Failure data analysis for preventive maintenance scheduling of a bottling company production system (2021)Open sourceNumber of events: 12.0 events · as reported: “Lc”
Show verbatim quote
Lb Lv Lc La Others Lf Lg 0 10 20 30 40 50 60 70 80 90 20% 40% 60% 80% 100% 40 17 12 8 6 2 1
- Failure data analysis for preventive maintenance scheduling of a bottling company production system (2021)Open sourceNumber of events: 8.00 events · as reported: “La”
Show verbatim quote
Lb Lv Lc La Others Lf Lg 0 10 20 30 40 50 60 70 80 90 20% 40% 60% 80% 100% 40 17 12 8 6 2 1
- Failure data analysis for preventive maintenance scheduling of a bottling company production system (2021)Open sourceNumber of events: 6.00 events · as reported: “Others”
Show verbatim quote
Lb Lv Lc La Others Lf Lg 0 10 20 30 40 50 60 70 80 90 20% 40% 60% 80% 100% 40 17 12 8 6 2 1
- Failure data analysis for preventive maintenance scheduling of a bottling company production system (2021)Open sourceNumber of events: 2.00 events · as reported: “Lf”
Show verbatim quote
Lb Lv Lc La Others Lf Lg 0 10 20 30 40 50 60 70 80 90 20% 40% 60% 80% 100% 40 17 12 8 6 2 1
- Failure data analysis for preventive maintenance scheduling of a bottling company production system (2021)Open sourceNumber of events: 1.00 events · as reported: “Lg”
Show verbatim quote
Lb Lv Lc La Others Lf Lg 0 10 20 30 40 50 60 70 80 90 20% 40% 60% 80% 100% 40 17 12 8 6 2 1
- Specific energy: 582 Wh/1000 Bottles · as reported: “Production”
Show verbatim quote
Production 119 4290.2 117 212.8 121 581.6
- Lost time: 3.50 h · as reported: “Prepared”
Show verbatim quote
Prepared 4.6 12.4 5.2 8.1 3.5 3.3
- Specific energy: 3.30 Wh/1000 Bottles · as reported: “Prepared”
Show verbatim quote
Prepared 4.6 12.4 5.2 8.1 3.5 3.3
- Lost time: 4.60 h · as reported: “Lack”
Show verbatim quote
Lack 0.1 1.3 0.0 0.0 4.6 4.4
- Specific energy: 4.40 Wh/1000 Bottles · as reported: “Lack”
Show verbatim quote
Lack 0.1 1.3 0.0 0.0 4.6 4.4
- Lost time: 4.80 h · as reported: “Tailback”
Show verbatim quote
Tailback 6.8 145.8 7.8 9.9 4.8 4.6
- Specific energy: 4.60 Wh/1000 Bottles · as reported: “Tailback”
Show verbatim quote
Tailback 6.8 145.8 7.8 9.9 4.8 4.6
- Lost time: 2.50 h · as reported: “Equipment failure”
Show verbatim quote
Equipment failure 8.1 195.6 4.9 6.5 2.5 2.2
- Specific energy: 2.20 Wh/1000 Bottles · as reported: “Equipment failure”
Show verbatim quote
Equipment failure 8.1 195.6 4.9 6.5 2.5 2.2
- Lost time: 31.7 h · as reported: “Held”
Show verbatim quote
Held 29.2 48.7 33 37.4 31.7 25.2
- Specific energy: 25.2 Wh/1000 Bottles · as reported: “Held”
Show verbatim quote
Held 29.2 48.7 33 37.4 31.7 25.2
- Specific energy: 621 Wh/1000 Bottles · as reported: “Total”
Show verbatim quote
Total 4694.0 274.8 621.2
- Enhancing Production Efficiency and Quality in the Carbonated Beverage Industry: A Lean Manufacturing Approach (2024)Open sourceNumber of events: 330 labels/month · as reported: “Wasted labels”
Show verbatim quote
Wasted labels (labels/month) 780 330 -57.69%
- Enhancing Production Efficiency and Quality in the Carbonated Beverage Industry: A Lean Manufacturing Approach (2024)Open sourceNumber of events: 780 labels/month · as reported: “Wasted labels”
Show verbatim quote
Wasted labels (labels/month) 780 330 -57.69%
- Analisa Efektifitas Mesin Palletizer Menggunakan Metode OEE Dan Identifikasi Kegagalan Dengan FMEA (2025)Open sourceLost time: 40.0 min · as reported: “Label”
Show verbatim quote
2 Label 40 12%
- Analisa Efektifitas Mesin Palletizer Menggunakan Metode OEE Dan Identifikasi Kegagalan Dengan FMEA (2025)Open sourceShare of lost time: 12.0 % · as reported: “Label”
Show verbatim quote
2 Label 40 12%
- Lost time: 0 min · as reported: “Planned losses”
Show verbatim quote
Planned losses (min) 0 160 0 0 0 160 7
- Lost time: 106 min · as reported: “Operational losses”
Show verbatim quote
Operational losses (min) 278 494 106 53 157 1088 48
- Lost time: 24.0 min · as reported: “Equipment losses”
Show verbatim quote
Equipment losses (min) 420 364 24 55 152 1015 44.8
- Lost time: 130 min · as reported: “Total Losses”
Show verbatim quote
Total Losses(min) 698 1018 130 108 309 2263
- Share of lost time: 5.80 % · as reported: “Total Losses”
Show verbatim quote
% of Losses 30.8 45 5.8 4.8 13.7
- Lost time: 106 min · as reported: “Labeller”
Show verbatim quote
Operational losses (min) | 278 | 494 | 106 | 53 | 157 | 1088 | 48
- Lost time: 24.0 min · as reported: “Labeller”
Show verbatim quote
Equipment losses (min) | 420 | 364 | 24 | 55 | 152 | 1015 | 44.8
- COMPARATIVE ANALYSIS OF PRODUCTION LINE EFFICIENCY UNDER VARYING DEMAND SCENARIOS USING MULTILAYER PERCEPTRON (2026)Open sourceLost time: 2.50 hrs · as reported: “Labeling Misalignment”
Show verbatim quote
3 Sprite 50cl PET 24 18,500 17,200 2.5 Labeling Misalignment 89.5 Changeover delay