Waiting for Raw Material or Ingredient Supply

In short

It appears in about 2 of every 100 lines studied.

When it appears, it takes on average about 58 % of the line's lost time. Reported by 6 of the 127 studies that could observe it (good evidence).

What happens

The line or a station stops producing because a required ingredient or component, such as syrup or a dietary supplement additive, is not physically available at the point of use when needed. The delay originates in upstream supply, internal logistics, or production scheduling rather than in a mechanical or control failure of the equipment itself.

What is done about it

Improve coordination between production scheduling, internal logistics, and suppliers, sizing intermediate buffers or batching of critical ingredients to absorb normal supply variability. Implement real-time inventory and level monitoring with early alerts so replenishment is triggered before the point of use runs dry.

Practical guidance written from engineering knowledge; it is not a statistical estimate.

1Probability and evidence

Pooled over all segments. A wide interval is a result: it states how much the evidence allows us to know.
Probability of presence
1.5% [0.5–3.5%]
Expected share of lost time
0.9% [0.3–2.1%]
Share of lost time when present
58% [48–68%]
Studies / units
127 / 161
Evidence grade
B

Grade B: 5 to 9 studies, or an interval width between 0.20 and 0.35.

2Probability by segment

Partially pooled estimates for each industry segment.
  • Dairy products
    1.6% [0.3–5.1%]13 studies
  • Soft drinks, bottled water and juices
    1.8% [0.4–5.1%]26 studies
  • Brewing, wine and spirits
    1.6% [0.3–4.9%]11 studies
  • Bakery and pasta
    1.9% [0.4–5.3%]24 studies
  • Meat, poultry and seafood
    2.3% [0.4–7.2%]9 studies
  • Fruit and vegetable processing
    2.5% [0.4–8.0%]7 studies
  • Grain and oilseed milling
    1.7% [0.3–5.3%]6 studies
  • Sugar and confectionery
    1.7% [0.3–5.1%]9 studies
  • Snacks, coffee, tea and other foods
    1.7% [0.3–5.3%]5 studies
  • Animal feed and pet food
    2.3% [0.4–7.4%]7 studies
  • Food manufacturing (unspecified or mixed)
    1.6% [0.3–5.1%]10 studies

3Mechanism, SCADA signature and countermeasure

Engineering guidance that helps recognise and address the cause; it is not part of the statistical estimate.

Mechanism

Engineering guidance

The line or a station stops producing because a required ingredient or component, such as syrup or a dietary supplement additive, is not physically available at the point of use when needed. The delay originates in upstream supply, internal logistics, or production scheduling rather than in a mechanical or control failure of the equipment itself.

How it looks in SCADA data

Engineering guidance

Machine or line state logs register an idle or wait status with no active fault or maintenance alarm, frequently preceded by buffer, tank, or hopper level signals dropping toward zero. Downstream equipment shows starvation patterns while no work order or repair event is linked to the stop in the maintenance system.

Countermeasure

Engineering guidance

Improve coordination between production scheduling, internal logistics, and suppliers, sizing intermediate buffers or batching of critical ingredients to absorb normal supply variability. Implement real-time inventory and level monitoring with early alerts so replenishment is triggered before the point of use runs dry.

4Sources

Every extracted datum with its study, value and verbatim quote.
  1. Lost time: 180 menit · as reported: “menunggu pengiriman”
    Show verbatim quote
    menunggu pengiriman 180 ✔ NVA
  2. Lost time: 180 min · as reported: “Menunggu pengiriman”
    Show verbatim quote
    Menunggu pengiriman 180
  3. Share of lost time: 66.0 % · as reported: “waiting time for syrup, filler, packer, sleever, conveyor”
    Show verbatim quote
    The machine downtime is recognized as a critical problem of the waiting time for syrup, filler, packer, sleever, conveyor, which accounts for 66 percent of the total time (as shown on Figure 2).
  4. Share of planned time: 66.0 % · as reported: “waiting time for syrup”
    Show verbatim quote
    The machine downtime is recognized as a critical problem of the waiting time for syrup, filler, packer, sleever, conveyor, which accounts for 66 percent of the total time (as shown on Figure 2).
  5. Lost time: 53.0 min · as reported: “Total waiting time”
    Show verbatim quote
    The total processing time was 1619 minutes, the total waiting time was 53 minutes, and the total lead time was 1672 minutes.
  6. Lost time: 15.0 min · as reported: “Waiting time”
    Show verbatim quote
    the waiting time to 15 minutes
  7. Lost time: 40.0 min · as reported: “Waiting time”
    Show verbatim quote
    Waiting time 40 min
  8. Lost time: 11.1 min · as reported: “Waiting time for dietary supplement”
    Show verbatim quote
    Waiting time for dietary supplement 11.06 min 1.95 min -9.11 min
  9. Lost time: 1.95 min · as reported: “Waiting time for dietary supplement”
    Show verbatim quote
    Waiting time for dietary supplement 11.06 min 1.95 min -9.11 min