Waiting for Raw Material or Ingredient Supply
In short
It appears in about 2 of every 100 lines studied.
When it appears, it takes on average about 58 % of the line's lost time. Reported by 6 of the 127 studies that could observe it (good evidence).
What happens
The line or a station stops producing because a required ingredient or component, such as syrup or a dietary supplement additive, is not physically available at the point of use when needed. The delay originates in upstream supply, internal logistics, or production scheduling rather than in a mechanical or control failure of the equipment itself.
What is done about it
Improve coordination between production scheduling, internal logistics, and suppliers, sizing intermediate buffers or batching of critical ingredients to absorb normal supply variability. Implement real-time inventory and level monitoring with early alerts so replenishment is triggered before the point of use runs dry.
Practical guidance written from engineering knowledge; it is not a statistical estimate.
1Probability and evidence
- Probability of presence
- 1.5% [0.5–3.5%]
- Expected share of lost time
- 0.9% [0.3–2.1%]
- Share of lost time when present
- 58% [48–68%]
- Studies / units
- 127 / 161
- Evidence grade
- B
Grade B: 5 to 9 studies, or an interval width between 0.20 and 0.35.
2Probability by segment
- Dairy products1.6% [0.3–5.1%]13 studies
- Soft drinks, bottled water and juices1.8% [0.4–5.1%]26 studies
- Brewing, wine and spirits1.6% [0.3–4.9%]11 studies
- Bakery and pasta1.9% [0.4–5.3%]24 studies
- Meat, poultry and seafood2.3% [0.4–7.2%]9 studies
- Fruit and vegetable processing2.5% [0.4–8.0%]7 studies
- Grain and oilseed milling1.7% [0.3–5.3%]6 studies
- Sugar and confectionery1.7% [0.3–5.1%]9 studies
- Snacks, coffee, tea and other foods1.7% [0.3–5.3%]5 studies
- Animal feed and pet food2.3% [0.4–7.4%]7 studies
- Food manufacturing (unspecified or mixed)1.6% [0.3–5.1%]10 studies
3Mechanism, SCADA signature and countermeasure
Mechanism
Engineering guidanceThe line or a station stops producing because a required ingredient or component, such as syrup or a dietary supplement additive, is not physically available at the point of use when needed. The delay originates in upstream supply, internal logistics, or production scheduling rather than in a mechanical or control failure of the equipment itself.
How it looks in SCADA data
Engineering guidanceMachine or line state logs register an idle or wait status with no active fault or maintenance alarm, frequently preceded by buffer, tank, or hopper level signals dropping toward zero. Downstream equipment shows starvation patterns while no work order or repair event is linked to the stop in the maintenance system.
Countermeasure
Engineering guidanceImprove coordination between production scheduling, internal logistics, and suppliers, sizing intermediate buffers or batching of critical ingredients to absorb normal supply variability. Implement real-time inventory and level monitoring with early alerts so replenishment is triggered before the point of use runs dry.
4Sources
- Penerapan value stream mapping untuk peningkatan produktivitas produksi okra beku di PT. MDT (2022)Open sourceLost time: 180 menit · as reported: “menunggu pengiriman”
Show verbatim quote
menunggu pengiriman 180 ✔ NVA
- Penerapan value stream mapping untuk peningkatan produktivitas produksi okra beku di PT. MDT (2022)Open sourceLost time: 180 min · as reported: “Menunggu pengiriman”
Show verbatim quote
Menunggu pengiriman 180
- An implementation of lean technology to improve the lead time of syrup batching process and reduce hot fill line downtime (2023)Open sourceShare of lost time: 66.0 % · as reported: “waiting time for syrup, filler, packer, sleever, conveyor”
Show verbatim quote
The machine downtime is recognized as a critical problem of the waiting time for syrup, filler, packer, sleever, conveyor, which accounts for 66 percent of the total time (as shown on Figure 2).
- An implementation of lean technology to improve the lead time of syrup batching process and reduce hot fill line downtime (2023)Open sourceShare of planned time: 66.0 % · as reported: “waiting time for syrup”
Show verbatim quote
The machine downtime is recognized as a critical problem of the waiting time for syrup, filler, packer, sleever, conveyor, which accounts for 66 percent of the total time (as shown on Figure 2).
- Using Lean Manufacturing Approach for Improvement in Food Manufacturing: Case Study from Egypt (2024)Open sourceLost time: 53.0 min · as reported: “Total waiting time”
Show verbatim quote
The total processing time was 1619 minutes, the total waiting time was 53 minutes, and the total lead time was 1672 minutes.
- The implementation of an integrated Lean Management-HACCP model: application in the food industry in Casablanca,Morocco (2025)Open sourceLost time: 15.0 min · as reported: “Waiting time”
Show verbatim quote
the waiting time to 15 minutes
- The implementation of an integrated Lean Management-HACCP model: application in the food industry in Casablanca,Morocco (2025)Open sourceLost time: 40.0 min · as reported: “Waiting time”
Show verbatim quote
Waiting time 40 min
- Production Management Model Based on Lean Manufacturing Tools and SLP to Increase Productivity in a Meatball (BARF) Plant (2026)Open sourceLost time: 11.1 min · as reported: “Waiting time for dietary supplement”
Show verbatim quote
Waiting time for dietary supplement 11.06 min 1.95 min -9.11 min
- Production Management Model Based on Lean Manufacturing Tools and SLP to Increase Productivity in a Meatball (BARF) Plant (2026)Open sourceLost time: 1.95 min · as reported: “Waiting time for dietary supplement”
Show verbatim quote
Waiting time for dietary supplement 11.06 min 1.95 min -9.11 min