Included study
Enhancing operational efficiency in craft beer production: implementation of lean manufacturing and TPM methodologies in SMES
1Bibliographic record
- Authors
- Perez Peralta, Ronald Wilmer, Meza Estrada, Adonis
- Year
- 2025
- Venue
- —
- DOI
- —
- Country
- Peru
- Segment
- Brewing, wine and spirits
- Process family
- Filling and packaging line
- Study type
- Before/after intervention
- Extraction scope
- Full text
- Size
- 1 plants · 1 lines · 1 machines
- Observation period
- —
- Data collection
- not_reported
- Intervention
Show the setting as described by the study
The set-up and format change time in the packaging machine to produce beer cans should be reduced with the help of distance optimization in relation to the components for changing the format and configuration of the equipment.
2Risk of bias
Scored with the rubric of the protocol: 2 low concern, 1 some concerns, 0 high concern.
Total score 9Moderate risk
| Item | Score |
|---|---|
| Is the observed line, machine or plant described well enough to classify its segment, process and equipment?Product or sector is given but the equipment or process is only partly described. | 1 / 2 |
| Is the observation period long enough and reported?Period not reported. | 0 / 2 |
| How were loss data collected?Interviews, estimates, or method not reported. | 0 / 2 |
| Are OEE, loading time and the loss categories defined explicitly?A standard definition is cited but its application is not shown. | 1 / 2 |
| Does the loss breakdown account for the total loss it claims to explain?Only the top causes are reported and the unexplained remainder can be computed. | 1 / 2 |
| Is there evidence of selective reporting of favourable results?Observational study, or intervention study that reports baseline and post-intervention data with the same method. | 2 / 2 |
| Are the reported numbers internally consistent?Recomputed totals, shares and OEE factors agree with the reported values within 2 percentage points. | 2 / 2 |
| Could conflicts of interest or the source of the data bias the result?Academic or independent study, or conflicts declared and unrelated to the result. | 2 / 2 |
3Extracted data
Each datum with its classification and the verbatim quote that states it.
| Reported cause | Loss category | Metric | Value | Extraction |
|---|---|---|---|---|
Setup timepackaging machine (filler)Show verbatim quote (Section 5, Results, Table 1)Setup time was reduced from 41 to 29 minutes, representing a 29% decrease. | Setup and adjustments | Lost time | 41.0 min | Single extractor |
Downtime of the processShow verbatim quote (Section 5, Results, Table 1)Process downtime decreased from 74 to 22.75 minutes, a 69% reduction. | Not classifiable from the report | Lost time | 74.0 min | Single extractor |
Rate of defective productsShow verbatim quote (Section 5, Results, Table 1)The rate of defective products was reduced from 2.97% to 1.30%, which is equivalent to a 56% decrease. | Process defects (scrap and rework) | Defect rate | 2.97 % | Single extractor |
—Show verbatim quote (Section 4.1, Initial Diagnosis)The operational efficiency of the case study stood at 78.10% during 2022, in contrast to the industry standard of 85% (Danlyan et al., 2020). | none | OEE | 78.1 % | Single extractor |
errors in the conduct of operationsShow verbatim quote (Section 4.1, Initial Diagnosis / Figure 2)Among the main causes identified, errors in the conduct of operations accounted for 39.20%, reprocessing constituted 13.95%, and process shutdowns due to machine failures covered 46.85%. | Not classifiable from the report | Share of lost time | 39.2 % | Single extractor |
reprocessingShow verbatim quote (Section 4.1, Initial Diagnosis / Figure 2)Among the main causes identified, errors in the conduct of operations accounted for 39.20%, reprocessing constituted 13.95%, and process shutdowns due to machine failures covered 46.85%. | Process defects (scrap and rework) | Share of lost time | 14.0 % | Single extractor |
process shutdowns due to machine failuresShow verbatim quote (Section 4.1, Initial Diagnosis / Figure 2)Among the main causes identified, errors in the conduct of operations accounted for 39.20%, reprocessing constituted 13.95%, and process shutdowns due to machine failures covered 46.85%. | Equipment failure (breakdowns) | Share of lost time | 46.9 % | Single extractor |
Setup timepackaging machine (filler)Show verbatim quote (Section 5, Results, Table 1)Setup time was reduced from 41 to 29 minutes, representing a 29% decrease. | Setup and adjustments | Lost time | 29.0 min | Single extractor |
Downtime of the processShow verbatim quote (Section 5, Results, Table 1)Process downtime decreased from 74 to 22.75 minutes, a 69% reduction. | Not classifiable from the report | Lost time | 22.8 min | Single extractor |
Rate of defective productsShow verbatim quote (Section 5, Results, Table 1)The rate of defective products was reduced from 2.97% to 1.30%, which is equivalent to a 56% decrease. | Process defects (scrap and rework) | Defect rate | 1.30 % | Single extractor |
—Filler/PackerShow verbatim quote (Table 1, Section 5. Results)SETUP Time (min) | 41 | 30 | 29 | -29% | Setup and adjustments | Lost time | 41.0 min | Single extractor |
—Filler/PackerShow verbatim quote (Table 1, Section 5. Results)Downtime of the process (min) | 74 | 45 | 22.75 | -69% | Not classifiable from the report | Lost time | 74.0 min | Single extractor |
—Filler/PackerShow verbatim quote (Table 1, Section 5. Results)Rate of defective products (%) | 2.97% | 1.50% | 1.30% | -56% | Process defects (scrap and rework) | Defect rate | 2.97 % | Single extractor |
—Filler/PackerShow verbatim quote (Table 1, Section 5. Results)SETUP Time (min) | 41 | 30 | 29 | -29% | Setup and adjustments | Lost time | 29.0 min | Single extractor |
—Filler/PackerShow verbatim quote (Table 1, Section 5. Results)Downtime of the process (min) | 74 | 45 | 22.75 | -69% | Not classifiable from the report | Lost time | 22.8 min | Single extractor |
—Filler/PackerShow verbatim quote (Table 1, Section 5. Results)Rate of defective products (%) | 2.97% | 1.50% | 1.30% | -56% | Process defects (scrap and rework) | Defect rate | 1.30 % | Single extractor |
Observation units
- Packaging line (filler/packer) - craft brewery case study · Filling · Baseline
- Packaging line (filler/packer) - craft brewery case study · Filling · After intervention
- Filler/Packer · Filling · Baseline
- Filler/Packer · Filling · After intervention