Enhancing Machinery Availability in a Food Company: An Integrated Approach Using TPM, SMED, and RCM Methodologies
1Bibliographic record
- Authors
- Sair Castañeda, Sharon Rodriguez, Orkun Yildiz, Duilio Aranda, José C. Alvarez
- Year
- 2024
- Venue
- Social Science Research Network
- Country
- Peru
- Segment
- Sugar and confectionery
- Process family
- Forming, baking and cooking
- Study type
- Before/after intervention
- Extraction scope
- Full text
- Size
- 1 plants · 1 lines · 2 machines
- Observation period
- 60 days
- Data collection
- manual_logs
- Intervention
Show the setting as described by the study
The company under study belongs to the food industry in Lima, Peru. It has five production lines: Chocolate Line, Confectionery, Instant Products, Cereals and Milling.
2Risk of bias
Scored with the rubric of the protocol: 2 low concern, 1 some concerns, 0 high concern.
Total score 10Moderate risk
| Item | Score |
|---|---|
| Is the observed line, machine or plant described well enough to classify its segment, process and equipment?Product, process and equipment are all described. | 2 / 2 |
| Is the observation period long enough and reported?Period reported and at least 30 days of production (or at least 100 recorded events). | 2 / 2 |
| How were loss data collected?Manual logs or maintenance records with unknown completeness. | 1 / 2 |
| Are OEE, loading time and the loss categories defined explicitly?Formulae or definitions are given for the reported metrics, including what counts as planned time. | 2 / 2 |
| Does the loss breakdown account for the total loss it claims to explain?Only selected causes are reported and the total is unknown. | 0 / 2 |
| Is there evidence of selective reporting of favourable results?Intervention study in which baseline and post-intervention periods differ in length or method. | 1 / 2 |
| Are the reported numbers internally consistent?Inconsistencies above 10 percentage points, or OEE factors above 100%. | 0 / 2 |
| Could conflicts of interest or the source of the data bias the result?Academic or independent study, or conflicts declared and unrelated to the result. | 2 / 2 |
3Extracted data
Each datum with its classification and the verbatim quote that states it.
| Reported cause | Loss category | Metric | Value | Extraction |
|---|---|---|---|---|
—Show verbatim quote (Conclusion)resulting in the optimization of the values of the MTBF MTTR indicators from 29.23 to 34.94 and from 7.72 to 8.72, respectively, with the application of the first pillar of TPM (Autonomous Maintenance) | Equipment failure (breakdowns) | Mean event duration | 8.72 h | Both extractors agreed |
—Show verbatim quote (Conclusion)resulting in the optimization of the values of the MTBF MTTR indicators from 29.23 to 34.94 and from 7.72 to 8.72, respectively, with the application of the first pillar of TPM (Autonomous Maintenance) | Equipment failure (breakdowns) | Time between events | 34.9 h | Both extractors agreed |
—Show verbatim quote (Discussion (Section 5))availability increases by 12.10%; initially, this parameter presented a percentage of 79.06%, and after the implementation, a value equal to 89.37% was obtained. | none | Availability | 89.4 % | Both extractors agreed |
—Show verbatim quote (Conclusion)resulting in the optimization of the values of the MTBF MTTR indicators from 29.23 to 34.94 and from 7.72 to 8.72, respectively, with the application of the first pillar of TPM (Autonomous Maintenance) | Equipment failure (breakdowns) | Mean event duration | 7.72 h | Both extractors agreed |
—Show verbatim quote (Conclusion)resulting in the optimization of the values of the MTBF MTTR indicators from 29.23 to 34.94 and from 7.72 to 8.72, respectively, with the application of the first pillar of TPM (Autonomous Maintenance) | Equipment failure (breakdowns) | Time between events | 29.2 h | Both extractors agreed |
—Show verbatim quote (Section 4.1)a gap in machinery availability has been identified, with the company under study reporting a value of 79.06%; however, the industry reflects that the value is acceptable greater than 90%. | none | Availability | 79.1 % | Both extractors agreed |
—Show verbatim quote (Section 3.3.3)Currently, there is 70.48% and its parameters of availability (78.05%), performance (94.86%) and quality (95.19%); and it is intended to reach an equal value of 85.02% | none | Quality | 95.2 % | Both extractors agreed |
—Show verbatim quote (Section 3.3.3)Currently, there is 70.48% and its parameters of availability (78.05%), performance (94.86%) and quality (95.19%); and it is intended to reach an equal value of 85.02% | none | Performance | 94.9 % | Both extractors agreed |
—Show verbatim quote (Table 1)OEE 78.05% 90.00% 11.95 pp | none | OEE | 78.1 % | Both extractors agreed |
Internal activities time (final)Show verbatim quote (Section 4.3.2 Phase 4)At the end of the activities, a final process time of 105.69 minutes was obtained, with eight internal and 25 external activities, each with a time of 25.62 and 80.07 minutes, respectively. | Setup and adjustments | Lost time | 25.6 min | Both extractors agreed |
Hours of preventive maintenance (scheduled), Month 2Show verbatim quote (Table 7)Month 2 12.00 20.00 8.00 | Planned downtime (scheduled maintenance, breaks, no demand) | Lost time | 12.0 h | Both extractors agreed |
Hours of preventive maintenance (scheduled), Month 1Show verbatim quote (Table 7)Month 1 14.00 25.00 11.00 | Planned downtime (scheduled maintenance, breaks, no demand) | Lost time | 14.0 h | Both extractors agreed |
Hours of factual preventive maintenance, Month 2Show verbatim quote (Table 7)Month 2 12.00 20.00 8.00 | Planned downtime (scheduled maintenance, breaks, no demand) | Lost time | 20.0 h | Both extractors agreed |
Hours of factual preventive maintenance, Month 1Show verbatim quote (Table 7)Month 1 14.00 25.00 11.00 | Planned downtime (scheduled maintenance, breaks, no demand) | Lost time | 25.0 h | Both extractors agreed |
—Show verbatim quote (Section 3.3.3)Currently, there is 70.48% and its parameters of availability (78.05%), performance (94.86%) and quality (95.19%); and it is intended to reach an equal value of 85.02% | none | OEE | 70.5 % | Single extractor |
—Show verbatim quote (Section 3.3.3)Currently, there is 70.48% and its parameters of availability (78.05%), performance (94.86%) and quality (95.19%); and it is intended to reach an equal value of 85.02% | none | Availability | 78.1 % | Single extractor |
Average Monthly installation time (2021)Show verbatim quote (Table 8)Month 1 31.17 22 18.5 41% | Setup and adjustments | Lost time | 31.2 not reported | Single extractor |
Total production time of changeover activitiesShow verbatim quote (Table 4)147.54 15 23 63.22 84.32 | Setup and adjustments | Lost time | 148 min | Single extractor |
Internal activitiesShow verbatim quote (Table 4)147.54 15 23 63.22 84.32 | Setup and adjustments | Number of events | 15.0 events | Single extractor |
External activitiesShow verbatim quote (Table 4)147.54 15 23 63.22 84.32 | Setup and adjustments | Number of events | 23.0 events | Single extractor |
Internal activities timeShow verbatim quote (Table 4)147.54 15 23 63.22 84.32 | Setup and adjustments | Lost time | 63.2 min | Single extractor |
External activities timeShow verbatim quote (Table 4)147.54 15 23 63.22 84.32 | Setup and adjustments | Lost time | 84.3 min | Single extractor |
Pilot test average monthly installation timeShow verbatim quote (Table 8)Month 1 31.17 22 18.5 41% | Setup and adjustments | Lost time | 18.5 not reported | Single extractor |
Final process time after SMED implementationShow verbatim quote (Section 4.3.2 Phase 4)At the end of the activities, a final process time of 105.69 minutes was obtained, with eight internal and 25 external activities, each with a time of 25.62 and 80.07 minutes, respectively. | Setup and adjustments | Lost time | 106 min | Single extractor |
External activities (final)Show verbatim quote (Section 4.3.2 Phase 4)At the end of the activities, a final process time of 105.69 minutes was obtained, with eight internal and 25 external activities, each with a time of 25.62 and 80.07 minutes, respectively. | Setup and adjustments | Number of events | 25.0 events | Single extractor |
External activities time (final)Show verbatim quote (Section 4.3.2 Phase 4)At the end of the activities, a final process time of 105.69 minutes was obtained, with eight internal and 25 external activities, each with a time of 25.62 and 80.07 minutes, respectively. | Setup and adjustments | Lost time | 80.1 min | Single extractor |
Extra hours, Month 1Show verbatim quote (Table 7)Month 1 14.00 25.00 11.00 | Planned downtime (scheduled maintenance, breaks, no demand) | Lost time | 11.0 h | Single extractor |
Extra hours, Month 2Show verbatim quote (Table 7)Month 2 12.00 20.00 8.00 | Planned downtime (scheduled maintenance, breaks, no demand) | Lost time | 8.00 h | Single extractor |
Breakdowns in the MachineryShow verbatim quote (Table 9)Breakdowns in the Machinery | 12.20% | 39.25% | Equipment failure (breakdowns) | Share of loss events | 12.2 % | Single extractor |
Breakdowns due to human errors in calibration or operationShow verbatim quote (Table 9)Breakdowns due to human errors in calibration or operation | 8.47% | 38.38% | Idling and minor stops (micro-stops) | Share of loss events | 8.47 % | Single extractor |
Observation units
- Confectionery line · Whole line or unspecified equipment · After intervention
- Confectionery line · Whole line or unspecified equipment · Baseline