Performance Analysis of Filling Machine Using Overall Equipment Effectiveness Metric in Beverage Company

Open source

1Bibliographic record

Authors
Didi Junaedi, Sakti Aji Lesmana, Iwan Roswandi, Ahmad Bramastro
Year
2023
Venue
International Journal of Advances in Scientific Research and Engineering
Country
Indonesia
Segment
Snacks, coffee, tea and other foods
Process family
Filling and packaging line
Study type
Single case study
Extraction scope
Full text
Size
1 plants · 1 lines · 1 machines
Observation period
120 days
Data collection
manual_logs
Intervention
Show the setting as described by the study
In Filling Line 3 machines, there are often losses caused by machine breaks, so the daily production target is not achieved.

2Risk of bias

Scored with the rubric of the protocol: 2 low concern, 1 some concerns, 0 high concern.
Total score 14Low risk
ItemScore
Is the observed line, machine or plant described well enough to classify its segment, process and equipment?Product, process and equipment are all described.2 / 2
Is the observation period long enough and reported?Period reported and at least 30 days of production (or at least 100 recorded events).2 / 2
How were loss data collected?Manual logs or maintenance records with unknown completeness.1 / 2
Are OEE, loading time and the loss categories defined explicitly?Formulae or definitions are given for the reported metrics, including what counts as planned time.2 / 2
Does the loss breakdown account for the total loss it claims to explain?The reported causes or categories sum to at least 90% of the stated total, or an explicit "other" class closes the balance.2 / 2
Is there evidence of selective reporting of favourable results?Observational study, or intervention study that reports baseline and post-intervention data with the same method.2 / 2
Are the reported numbers internally consistent?Small inconsistencies (2 to 10 percentage points) or values that cannot be cross-checked.1 / 2
Could conflicts of interest or the source of the data bias the result?Academic or independent study, or conflicts declared and unrelated to the result.2 / 2

3Extracted data

Each datum with its classification and the verbatim quote that states it.
Reported causeLoss categoryMetricValueExtraction
Setup & Adjustmentfilling machine
Show verbatim quote (Conclusion)
The second is Setup and Adjustment (30.7%), or equal to 2,235 minutes from data collection for December 2021 – March 2022.
Setup and adjustmentsLost time2,235 minBoth extractors agreed
Equipment Failurefilling machine
Show verbatim quote (Conclusion)
the Equipment Failure factor (52.7%), or equivalent,t to 3,835 minutes
Equipment failure (breakdowns)Lost time3,835 minBoth extractors agreed
Reduced Speed Lossesfilling machine
Show verbatim quote (Table 5)
Reduced Speed Losses 0 0 100
Reduced speedShare of lost time0 %Both extractors agreed
Reduced Speed Lossesfilling machine
Show verbatim quote (Table 5)
Reduced Speed Losses 0 0 100
Reduced speedLost time0 minBoth extractors agreed
Defect Processfilling machine
Show verbatim quote (Table 5)
Defect Process 585 8 91,4
Process defects (scrap and rework)Share of lost time8.00 %Both extractors agreed
Defect Processfilling machine
Show verbatim quote (Table 5)
Defect Process 585 8 91,4
Process defects (scrap and rework)Lost time585 minBoth extractors agreed
—filling machine
Show verbatim quote (Table 2)
Mar 22 286.700 0,02 0,0265 7.196 86,2 75,4 97,5 63,3
noneQuality97.5 %Both extractors agreed
—filling machine
Show verbatim quote (Table 2)
Mar 22 286.700 0,02 0,0265 7.196 86,2 75,4 97,5 63,3
nonePerformance75.4 %Both extractors agreed
—filling machine
Show verbatim quote (Table 2)
Mar 22 286.700 0,02 0,0265 7.196 86,2 75,4 97,5 63,3
noneAvailability86.2 %Both extractors agreed
—filling machine
Show verbatim quote (Table 2)
Feb 22 235.350 0,02 0,0273 4.635 85,3 73 98 61
noneQuality98.0 %Both extractors agreed
—filling machine
Show verbatim quote (Table 2)
Feb 22 235.350 0,02 0,0273 4.635 85,3 73 98 61
nonePerformance73.0 %Both extractors agreed
—filling machine
Show verbatim quote (Table 2)
Feb 22 235.350 0,02 0,0273 4.635 85,3 73 98 61
noneAvailability85.3 %Both extractors agreed
—filling machine
Show verbatim quote (Table 2)
Of the 21 256.035 0,02 0,0273 9.391 75,8 73,1 96,3 53,4
noneQuality96.3 %Both extractors agreed
—filling machine
Show verbatim quote (Table 2)
Of the 21 256.035 0,02 0,0273 9.391 75,8 73,1 96,3 53,4
nonePerformance73.1 %Both extractors agreed
—filling machine
Show verbatim quote (Table 2)
Of the 21 256.035 0,02 0,0273 9.391 75,8 73,1 96,3 53,4
noneAvailability75.8 %Both extractors agreed
—filling machine
Show verbatim quote (Table 2)
Jan 22 262.800 0,02 0,0262 8.221 82,1 76,2 96,9 60,6
noneQuality96.9 %Both extractors agreed
—filling machine
Show verbatim quote (Table 2)
Jan 22 262.800 0,02 0,0262 8.221 82,1 76,2 96,9 60,6
nonePerformance76.2 %Both extractors agreed
—filling machine
Show verbatim quote (Table 2)
Jan 22 262.800 0,02 0,0262 8.221 82,1 76,2 96,9 60,6
noneAvailability82.1 %Both extractors agreed
—filling machine
Show verbatim quote (Abstract)
the Overall Equipment Effectiveness (OEE) value for the period of December 2021 (53.4%), January 2022 (60.6%), February 2022 (61%), and March 2022 (63.3%)
noneOEE63.3 %Both extractors agreed
—filling machine
Show verbatim quote (Abstract)
the Overall Equipment Effectiveness (OEE) value for the period of December 2021 (53.4%), January 2022 (60.6%), February 2022 (61%), and March 2022 (63.3%)
noneOEE61.0 %Both extractors agreed
—filling machine
Show verbatim quote (Abstract)
the Overall Equipment Effectiveness (OEE) value for the period of December 2021 (53.4%), January 2022 (60.6%), February 2022 (61%), and March 2022 (63.3%)
noneOEE60.6 %Both extractors agreed
—filling machine
Show verbatim quote (Abstract)
the Overall Equipment Effectiveness (OEE) value for the period of December 2021 (53.4%), January 2022 (60.6%), February 2022 (61%), and March 2022 (63.3%)
noneOEE53.4 %Both extractors agreed
Equipment Failurefilling machine
Show verbatim quote (Conclusion)
the Equipment Failure factor (52.7%), or equivalent,t to 3,835 minutes
Equipment failure (breakdowns)Share of lost time52.7 %Single extractor
Setup & Adjustmentfilling machine
Show verbatim quote (Conclusion)
The second is Setup and Adjustment (30.7%), or equal to 2,235 minutes from data collection for December 2021 – March 2022.
Setup and adjustmentsShare of lost time30.7 %Single extractor
Idling & Minor Stoppagesfilling machine
Show verbatim quote (Table 5)
Idling & Minor Stoppages 524 7,2 98,6
Idling and minor stops (micro-stops)Lost time524 minSingle extractor
Idling & Minor Stoppagesfilling machine
Show verbatim quote (Table 5)
Idling & Minor Stoppages 524 7,2 98,6
Idling and minor stops (micro-stops)Share of lost time7.20 %Single extractor
Reduced Yieldfilling machine
Show verbatim quote (Table 5)
Reduced Yield 99 1,4 100
Start-up losses (reduced yield)Lost time99.0 minSingle extractor
Reduced Yieldfilling machine
Show verbatim quote (Table 5)
Reduced Yield 99 1,4 100
Start-up losses (reduced yield)Share of lost time1.40 %Single extractor

Observation units

  • Filling Line 3 · Filling · Baseline