Included study
Analisis Total Productive Maintenance (TPM) dengan Menggunakan Metode Overall Equipment Effectiveness (OEE) pada Mesin Blowing
1Bibliographic record
- Authors
- Mochammad Rizal Ardiansyah, Nuriyanto Nuriyanto
- Year
- 2025
- Venue
- Jurnal Teknik Industri Terintegrasi
- Country
- —
- Segment
- Soft drinks, bottled water and juices
- Process family
- Filling and packaging line
- Study type
- Single case study
- Extraction scope
- Full text
- Size
- 1 plants · 1 lines · 1 machines
- Observation period
- 28 days
- Data collection
- manual_logs
- Intervention
Show the setting as described by the study
penelitian ini difokuskan pada mesin Blowing, yang merupakan salah satu mesin utama dalam proses produksi di PT. XYZ
2Risk of bias
Scored with the rubric of the protocol: 2 low concern, 1 some concerns, 0 high concern.
Total score 13Low risk
| Item | Score |
|---|---|
| Is the observed line, machine or plant described well enough to classify its segment, process and equipment?Product, process and equipment are all described. | 2 / 2 |
| Is the observation period long enough and reported?Period reported but shorter than 30 days, or only the number of shifts is given. | 1 / 2 |
| How were loss data collected?Manual logs or maintenance records with unknown completeness. | 1 / 2 |
| Are OEE, loading time and the loss categories defined explicitly?Formulae or definitions are given for the reported metrics, including what counts as planned time. | 2 / 2 |
| Does the loss breakdown account for the total loss it claims to explain?Only the top causes are reported and the unexplained remainder can be computed. | 1 / 2 |
| Is there evidence of selective reporting of favourable results?Observational study, or intervention study that reports baseline and post-intervention data with the same method. | 2 / 2 |
| Are the reported numbers internally consistent?Recomputed totals, shares and OEE factors agree with the reported values within 2 percentage points. | 2 / 2 |
| Could conflicts of interest or the source of the data bias the result?Academic or independent study, or conflicts declared and unrelated to the result. | 2 / 2 |
3Extracted data
Each datum with its classification and the verbatim quote that states it.
| Reported cause | Loss category | Metric | Value | Extraction |
|---|---|---|---|---|
Mold Safety Cam ClosureMesin BlowingShow verbatim quote (Tabel 9)Mold Safety Cam Closure 135 | Not classifiable from the report | Lost time | 135 menit | Adjudicated |
Oven Wheel IntervensionMesin BlowingShow verbatim quote (Tabel 9)Oven Wheel Intervension 149 | Not classifiable from the report | Lost time | 149 menit | Adjudicated |
Bottle Fallen MoldMesin BlowingShow verbatim quote (Tabel 9)Bottle Fallen Mold 253 | Idling and minor stops (micro-stops) | Lost time | 253 menit | Both extractors agreed |
—Mesin BlowingShow verbatim quote (Tabel 7)Rata - Rata 93,90 90,79 99,77 84,99 85% Tidak memenuhi standart | none | OEE | 85.0 % | Both extractors agreed |
—Mesin BlowingShow verbatim quote (Tabel 6)Rata - rata 2207238 5322 99,76 99% Memenuhi Standart | none | Quality | 99.8 % | Both extractors agreed |
—Mesin BlowingShow verbatim quote (Tabel 5)Rata - rata 2207238 0,003 7294 90,79 95% Tidak Memenuhi standart | none | Performance | 90.8 % | Both extractors agreed |
—Mesin BlowingShow verbatim quote (Tabel 4)Rata - rata 7765 7294 93,90 90% Memenuhi Standart | none | Availability | 93.9 % | Both extractors agreed |
Bottle Not EkstrakMesin BlowingShow verbatim quote (Tabel 9)Bottle Not Ekstrak 587 | Idling and minor stops (micro-stops) | Lost time | 587 menit | Both extractors agreed |
Equipment Failure LossesMesin BlowingShow verbatim quote (Tabel 8)Rata - rata 6,10 0,95 11,47 0,00 0,00 0,21 | Equipment failure (breakdowns) | Share of lost time | 6.10 % | Single extractor |
Set Up & Adjustment LossesMesin BlowingShow verbatim quote (Tabel 8)Rata - rata 6,10 0,95 11,47 0,00 0,00 0,21 | Setup and adjustments | Share of lost time | 0.950 % | Single extractor |
Idling & Minor Stoppage LossesMesin BlowingShow verbatim quote (Tabel 8)Rata - rata 6,10 0,95 11,47 0,00 0,00 0,21 | Idling and minor stops (micro-stops) | Share of lost time | 11.5 % | Single extractor |
Reduce Speed LossesMesin BlowingShow verbatim quote (Tabel 8)Rata - rata 6,10 0,95 11,47 0,00 0,00 0,21 | Reduced speed | Share of lost time | 0 % | Single extractor |
Reduce YieldMesin BlowingShow verbatim quote (Tabel 8)Rata - rata 6,10 0,95 11,47 0,00 0,00 0,21 | Start-up losses (reduced yield) | Share of lost time | 0 % | Single extractor |
Product Defect LossesMesin BlowingShow verbatim quote (Tabel 8)Rata - rata 6,10 0,95 11,47 0,00 0,00 0,21 | Process defects (scrap and rework) | Share of lost time | 0.210 % | Single extractor |
Downtime TerencanaMesin BlowingShow verbatim quote (Tabel 1 (Data Produksi dan Downtime Week 47-50 2024))Rata - rata 2207238 2500000 5322 0,0030 156 470,75 | Planned downtime (scheduled maintenance, breaks, no demand) | Lost time | 156 menit | Single extractor |
Downtime Tidak TerencanaMesin BlowingShow verbatim quote (Tabel 1 (Data Produksi dan Downtime Week 47-50 2024))Rata - rata 2207238 2500000 5322 0,0030 156 470,75 | Not classifiable from the report | Lost time | 471 menit | Single extractor |
—Mesin BlowingShow verbatim quote (Bagian 1. Pendahuluan)Jika dibandingkan dengan total plan time sebesar 31.680 menit, downtime pada mesin Blowing mencapai 3,54%, menunjukkan bahwa mesin ini memiliki kontribusi signifikan terhadap total kehilangan waktu produksi. | Not classifiable from the report | Share of planned time | 3.54 % | Single extractor |
—Mesin BlowingShow verbatim quote (Bagian 1. Pendahuluan)tercatat bahwa mesin Blowing mengalami downtime selama 1.124 menit, yang merupakan jumlah waktu henti tertinggi dibandingkan area produksi lainnya | Not classifiable from the report | Lost time | 1,124 menit | Single extractor |
Bottle Not EkstrakMesin BlowingShow verbatim quote (Analisa Data - Diagram Pareto)hasil dari diagram pareto menunjukkan bahwa jenis downtime terbesar adalah Bottle Not Ektrak, yang mencakup 52% dari total waktu henti mesin. | Idling and minor stops (micro-stops) | Share of lost time | 52.0 % | Single extractor |
—AutopackerShow verbatim quote (Tabel 1. Data Downtime W47-50)Autopacker 226 0,71% | Not classifiable from the report | Lost time | 226 menit | Single extractor |
—AutopackerShow verbatim quote (Tabel 1. Data Downtime W47-50)Autopacker 226 0,71% | Not classifiable from the report | Share of planned time | 0.710 % | Single extractor |
—PalletizerShow verbatim quote (Tabel 1. Data Downtime W47-50)Palletizer 215 0,67% | Not classifiable from the report | Lost time | 215 menit | Single extractor |
—PalletizerShow verbatim quote (Tabel 1. Data Downtime W47-50)Palletizer 215 0,67% | Not classifiable from the report | Share of planned time | 0.670 % | Single extractor |
—LabelShow verbatim quote (Tabel 1. Data Downtime W47-50)Label 159 0,50% | Not classifiable from the report | Lost time | 159 menit | Single extractor |
—LabelShow verbatim quote (Tabel 1. Data Downtime W47-50)Label 159 0,50% | Not classifiable from the report | Share of planned time | 0.500 % | Single extractor |
—FillingShow verbatim quote (Tabel 1. Data Downtime W47-50)Filling 159 0,50% | Not classifiable from the report | Lost time | 159 menit | Single extractor |
—FillingShow verbatim quote (Tabel 1. Data Downtime W47-50)Filling 159 0,50% | Not classifiable from the report | Share of planned time | 0.500 % | Single extractor |
—Show verbatim quote (Table 8. Perhitungan Six Big Loss W47 – 50 2024)Rata - rata 6,10 0,95 11,47 0,00 0,00 0,21 | Equipment failure (breakdowns) | Share of planned time | 6.10 % | Single extractor |
—Show verbatim quote (Table 8. Perhitungan Six Big Loss W47 – 50 2024)Rata - rata 6,10 0,95 11,47 0,00 0,00 0,21 | Setup and adjustments | Share of planned time | 0.950 % | Single extractor |
—Show verbatim quote (Table 8. Perhitungan Six Big Loss W47 – 50 2024)Rata - rata 6,10 0,95 11,47 0,00 0,00 0,21 | Idling and minor stops (micro-stops) | Share of planned time | 11.5 % | Single extractor |
—Show verbatim quote (Table 8. Perhitungan Six Big Loss W47 – 50 2024)Rata - rata 6,10 0,95 11,47 0,00 0,00 0,21 | Process defects (scrap and rework) | Share of planned time | 0.210 % | Single extractor |
Observation units
- Mesin Blowing · Forming, moulding and depositing · Baseline
- Autopacker · Packaging (forming, sealing, wrapping, case packing, palletizing) · Baseline
- Palletizer · Packaging (forming, sealing, wrapping, case packing, palletizing) · Baseline
- Label · Labeling and coding · Baseline
- Filling · Filling · Baseline
- Blowing · Forming, moulding and depositing · Baseline