Automatic OEE Data Collection and Alert System for Food Industry

Open source

1Bibliographic record

Authors
Ruly Sumargo, Amelia Makmur
Year
2023
Venue
SinkrOn
Country
—
Segment
Food manufacturing (unspecified or mixed)
Process family
Filling and packaging line
Study type
Before/after intervention
Extraction scope
Full text
Size
1 plants · 1 lines · 15 machines
Observation period
365 days
Data collection
automatic_monitoring
Intervention
Show the setting as described by the study
Current OEE system were assign to handled 15 packaging machines as shown by Figure 6 above.

2Risk of bias

Scored with the rubric of the protocol: 2 low concern, 1 some concerns, 0 high concern.
Total score 13Low risk
ItemScore
Is the observed line, machine or plant described well enough to classify its segment, process and equipment?Product or sector is given but the equipment or process is only partly described.1 / 2
Is the observation period long enough and reported?Period reported and at least 30 days of production (or at least 100 recorded events).2 / 2
How were loss data collected?Automatic line monitoring, or systematic logs covering every stop in the period.2 / 2
Are OEE, loading time and the loss categories defined explicitly?Formulae or definitions are given for the reported metrics, including what counts as planned time.2 / 2
Does the loss breakdown account for the total loss it claims to explain?The reported causes or categories sum to at least 90% of the stated total, or an explicit "other" class closes the balance.2 / 2
Is there evidence of selective reporting of favourable results?Intervention study in which baseline and post-intervention periods differ in length or method.1 / 2
Are the reported numbers internally consistent?Recomputed totals, shares and OEE factors agree with the reported values within 2 percentage points.2 / 2
Could conflicts of interest or the source of the data bias the result?Authors are employees of the plant or of an equipment/software vendor; no declaration.1 / 2

3Extracted data

Each datum with its classification and the verbatim quote that states it.
Reported causeLoss categoryMetricValueExtraction
Untrained operator not able to run at nominal speed
Show verbatim quote (Table 4)
Untrained operator not able to run at nominal speed 3.17% 4.82% 3.14%
Reduced speedShare of lost time3.17 %Both extractors agreed
Product out of spec at process start of run
Show verbatim quote (Table 4)
Product out of spec at process start of run 44.24% 46.10% 44.58%
Start-up losses (reduced yield)Share of lost time44.2 %Both extractors agreed
Damage product after maintenance activity
Show verbatim quote (Table 4)
Damage product after maintenance activity 6.03% 6.29% 5.97%
Start-up losses (reduced yield)Share of lost time6.03 %Both extractors agreed
Running lower than nominal speed
Show verbatim quote (Table 4)
Running lower than nominal speed 8.99% 8.77% 13.44%
Reduced speedShare of lost time8.99 %Both extractors agreed
Major component failure/Cutting Blade Change
Show verbatim quote (Table 4)
Major component failure/ Cutting Blade Change 0.79% 0.77% 0.71%
Equipment failure (breakdowns)Share of lost time0.790 %Both extractors agreed
Fallen product and Cleaning
Show verbatim quote (Table 4)
Fallen product and Cleaning 7.94% 10.09% 31.47%
Idling and minor stops (micro-stops)Share of lost time7.94 %Both extractors agreed
Blockages/Process Failure
Show verbatim quote (Table 4)
Blockages/Process Failure 67.46% 63.60% 25.76%
Idling and minor stops (micro-stops)Share of lost time67.5 %Both extractors agreed
Labor shortage/Break Time
Show verbatim quote (Table 4)
Labor shortage/Break Time 36.74% 36.85% 37.87%
Organizational or external stops (material or personnel shortage, utilities outage)Share of lost time36.7 %Adjudicated
Untrained operator not able to run at nominal speed
Show verbatim quote (Table 4)
Untrained operator not able to run at nominal speed 3.17% 4.82% 3.14%
Reduced speedShare of lost time3.14 %Both extractors agreed
Measurement Adjustment
Show verbatim quote (Table 4)
Measurement Adjustment 2.19% 2.15% 1.49%
Setup and adjustmentsShare of lost time2.19 %Both extractors agreed
Material availability
Show verbatim quote (Table 4)
Material availability 10.12% 12.16% 3.19%
Organizational or external stops (material or personnel shortage, utilities outage)Share of lost time10.1 %Adjudicated
Product out of spec
Show verbatim quote (Table 4)
Product out of spec 44.24% 41.90% 44.17%
Process defects (scrap and rework)Share of lost time44.2 %Both extractors agreed
Planned maintenance
Show verbatim quote (Table 4)
Planned maintenance 35.09% 34.48% 39.78%
Planned downtime (scheduled maintenance, breaks, no demand)Share of lost time35.1 %Adjudicated
—
Show verbatim quote (Table 3)
Availability (%) 71.49% 56.47% 74.85%
noneAvailability71.5 %Both extractors agreed
—
Show verbatim quote (Table 3)
Performance (%) 91.52% 90.29% 98.09%
nonePerformance91.5 %Both extractors agreed
Minor Stoppage
Show verbatim quote (Table 4)
Minor Stoppage 6.08% 3.95% 11.65%
Idling and minor stops (micro-stops)Share of lost time6.08 %Both extractors agreed
Major component failure/Cutting Blade Change
Show verbatim quote (Table 4)
Major component failure/ Cutting Blade Change 0.79% 0.77% 0.71%
Equipment failure (breakdowns)Share of lost time0.710 %Both extractors agreed
Product out of spec at process start of run
Show verbatim quote (Table 4)
Product out of spec at process start of run 44.24% 46.10% 44.58%
Start-up losses (reduced yield)Share of lost time44.6 %Both extractors agreed
Misalignment
Show verbatim quote (Table 4)
Misalignment 6.35% 8.77% 14.56%
Idling and minor stops (micro-stops)Share of lost time6.35 %Both extractors agreed
—
Show verbatim quote (Table 3)
Quality (%) 98.91% 98.95% 99.11%
noneQuality98.9 %Both extractors agreed
Changeover
Show verbatim quote (Table 4)
Changeover 14.62% 12.65% 16.58%
Setup and adjustmentsShare of lost time14.6 %Both extractors agreed
Breakdown
Show verbatim quote (Table 4)
Breakdown 0.45% 0.94% 0.38%
Equipment failure (breakdowns)Share of lost time0.450 %Both extractors agreed
—
Show verbatim quote (Table 3)
OEE (%) 64.71% 50.45% 72.77%
noneOEE64.7 %Both extractors agreed
Scrap
Show verbatim quote (Table 4)
Scrap 5.48% 5.71% 5.28%
Process defects (scrap and rework)Share of lost time5.48 %Both extractors agreed
—
Show verbatim quote (Table 4)
Accumulated time losses > 1 hour 9.02% 3.40% 4.22%
Not classifiable from the reportShare of lost time9.02 %Both extractors agreed
—
Show verbatim quote (Table 4)
Accumulated time losses > 1 hour 9.02% 3.40% 4.22%
Not classifiable from the reportShare of lost time4.22 %Both extractors agreed
—
Show verbatim quote (Table 3)
Availability (%) 71.49% 56.47% 74.85%
noneAvailability74.9 %Single extractor
—
Show verbatim quote (Table 3)
Performance (%) 91.52% 90.29% 98.09%
nonePerformance98.1 %Single extractor
—
Show verbatim quote (Table 3)
Quality (%) 98.91% 98.95% 99.11%
noneQuality99.1 %Single extractor
—
Show verbatim quote (Table 3)
OEE (%) 64.71% 50.45% 72.77%
noneOEE72.8 %Single extractor
Breakdown
Show verbatim quote (Table 4)
Breakdown 0.45% 0.94% 0.38%
Equipment failure (breakdowns)Share of lost time0.380 %Single extractor
Planned maintenance
Show verbatim quote (Table 4)
Planned maintenance 35.09% 34.48% 39.78%
Setup and adjustmentsShare of lost time39.8 %Single extractor
Material availability
Show verbatim quote (Table 4)
Material availability 10.12% 12.16% 3.19%
Setup and adjustmentsShare of lost time3.19 %Single extractor
Labor shortage/Break Time
Show verbatim quote (Table 4)
Labor shortage/Break Time 36.74% 36.85% 37.87%
Setup and adjustmentsShare of lost time37.9 %Single extractor
Changeover
Show verbatim quote (Table 4)
Changeover 14.62% 12.65% 16.58%
Setup and adjustmentsShare of lost time16.6 %Single extractor
Measurement Adjustment
Show verbatim quote (Table 4)
Measurement Adjustment 2.19% 2.15% 1.49%
Setup and adjustmentsShare of lost time1.49 %Single extractor
Fallen product and Cleaning
Show verbatim quote (Table 4)
Fallen product and Cleaning 7.94% 10.09% 31.47%
Idling and minor stops (micro-stops)Share of lost time31.5 %Single extractor
Blockages/Process Failure
Show verbatim quote (Table 4)
Blockages/Process Failure 67.46% 63.60% 25.76%
Idling and minor stops (micro-stops)Share of lost time25.8 %Single extractor
Misalignment
Show verbatim quote (Table 4)
Misalignment 6.35% 8.77% 14.56%
Idling and minor stops (micro-stops)Share of lost time14.6 %Single extractor
Minor Stoppage
Show verbatim quote (Table 4)
Minor Stoppage 6.08% 3.95% 11.65%
Idling and minor stops (micro-stops)Share of lost time11.7 %Single extractor
Running lower than nominal speed
Show verbatim quote (Table 4)
Running lower than nominal speed 8.99% 8.77% 13.44%
Reduced speedShare of lost time13.4 %Single extractor
Product out of spec
Show verbatim quote (Table 4)
Product out of spec 44.24% 41.90% 44.17%
Process defects (scrap and rework)Share of lost time44.2 %Single extractor
Scrap
Show verbatim quote (Table 4)
Scrap 5.48% 5.71% 5.28%
Process defects (scrap and rework)Share of lost time5.28 %Single extractor
Damage product after maintenance activity
Show verbatim quote (Table 4)
Damage product after maintenance activity 6.03% 6.29% 5.97%
Start-up losses (reduced yield)Share of lost time5.97 %Single extractor

Observation units

  • Food packaging line (average of 15 packaging machines) · Packaging (forming, sealing, wrapping, case packing, palletizing) · Baseline
  • Food packaging line (average of 15 packaging machines) · Packaging (forming, sealing, wrapping, case packing, palletizing) · After intervention