Forming, baking and cooking

Industrial bread

Dough is mixed, divided and proofed, baked in a tunnel oven, cooled, sliced and packed.

In short

This is the line

Each station shows how far it can go according to physics. Select one to see its detail.

Out of every 100 hours planned for production
  1. 67produce

    Typical of the plants studied: the equivalent of 67 hours of good product at full speed (an OEE of 67 %).

  2. 19can be recovered

    The physics of this process allows up to 86 out of 100. This band is the possible improvement.

  3. 14are a physical limit

    No plant avoids them: mandatory cleaning and the minimum times needed to heat, cool or fill.

The typical value comes from 21 studies of Bakery and pasta, Forming, baking and cooking.

The most limiting station is Refrigeration and freezing: it reaches 86 % at most.

Where the time is lost

  • Breakdowns25 %

    The machine stops because something fails and has to be repaired.

  • Reduced speed23 %

    The line runs, but slower than it can.

  • Changeovers and adjustments19 %

    Time between one product and the next: format change, cleaning, warm-up and fine tuning.

  • Minor stops19 %

    Short stops the operator clears without maintenance: jams, waiting, blocked sensors.

  • Defects10 %

    Product that comes out wrong and is scrapped or reworked.

  • Start-up losses3 %

    Product lost while the line settles after starting.

Split estimated from 18 studies of Bakery and pasta, Forming, baking and cooking.

What most often stops lines like this one

Causes reported by the studies, from the most to the least frequent.

  1. Packaging machine breakdownappears in about 4 of every 100 lines studiedPackaging (forming, sealing, wrapping, case packing, palletizing) · Breakdowns · strong evidence
  2. Forming/blow-moulding machine breakdownappears in about 2 of every 100 lines studiedForming, moulding and depositing · Breakdowns · good evidence
  3. Minor stoppages on forming machinesappears in about 2 of every 100 lines studiedForming, moulding and depositing · Minor stops · good evidence
  4. Reduced speed operation of forming equipmentappears in about 2 of every 100 lines studiedForming, moulding and depositing · Reduced speed · limited evidence
  5. Unspecified packaging defectappears in about 2 of every 100 lines studiedPackaging (forming, sealing, wrapping, case packing, palletizing) · Defects · good evidence

See the technical detail

Technical detail

Uncertainty intervals, physical models per station and sources, for anyone who wants to check each figure.

1Why it stops: the six big losses

The most probable situations inside each loss, according to 429 published studies. The percentage estimates the probability that a food and beverage line shows that cause; the number of studies reporting it is given below.
Availability

Equipment failure (breakdowns)

25 %of the lost time · 95% interval: 13–38 %
In the operations of this process
  1. Packaging machine breakdownPackaging (forming, sealing, wrapping, case packing, palletizing)4.4 %A1.9–8.4 %· 12 of 112 studies report it
  2. Forming/blow-moulding machine breakdownForming, moulding and depositing2.3 %B0.7–5.3 %· 5 of 76 studies report it
  3. Forming machine drive/chain mechanical failureForming, moulding and depositing1.1 %C0.2–3.0 %· 2 of 76 studies report it
  4. Basic Condition and Operating Standard Non-CompliancePackaging (forming, sealing, wrapping, case packing, palletizing)1.1 %C0.3–2.7 %· 3 of 112 studies report it
In any line
  1. Unplanned equipment breakdownWhole line or unspecified equipment11 %A6.1–18 %· 30 of 127 studies report it
  2. Mechanical, electrical or pneumatic component failureWhole line or unspecified equipment1.4 %B0.5–3.2 %· 5 of 127 studies report it

Setup and adjustments

19 %of the lost time · 95% interval: 8–34 %
In the operations of this process
  1. Syrup batching changeover and setup timeMixing and blending1.3 %C0.3–3.8 %· 2 of 31 studies report it
  2. Manual cleaning of mixing equipment during changeoverMixing and blending1.3 %C0.2–3.7 %· 2 of 31 studies report it
  3. Format/mould changeover on forming equipmentForming, moulding and depositing1.3 %C0.3–3.2 %· 3 of 76 studies report it
  4. Packaging Equipment Setup and AdjustmentPackaging (forming, sealing, wrapping, case packing, palletizing)1.0 %C0.3–2.5 %· 3 of 112 studies report it
In any line
  1. Changeover / setup timeWhole line or unspecified equipment11 %A5.6–17 %· 28 of 127 studies report it
  2. Cleaning and sanitation downtimeWhole line or unspecified equipment1.0 %C0.3–2.3 %· 3 of 127 studies report it
Performance

Idling and minor stops (micro-stops)

19 %of the lost time · 95% interval: 8–33 %
In the operations of this process
  1. Minor stoppages on forming machinesForming, moulding and depositing2.2 %B0.6–5.1 %· 5 of 76 studies report it
  2. Waiting time due to line imbalance at cutting stationCutting, slicing and deboning0.9 %D0.1–2.7 %· 1 of 39 studies reports it
  3. Packaging/filling seal and handling mechanism faultPackaging (forming, sealing, wrapping, case packing, palletizing)0.8 %C0.2–2.0 %· 2 of 112 studies report it
  4. Palletizer minor stoppage (misalignment, jam or blockage)Packaging (forming, sealing, wrapping, case packing, palletizing)0.7 %C0.2–1.8 %· 2 of 112 studies report it
In any line
  1. Idling and minor stoppagesWhole line or unspecified equipment1.9 %B0.6–4.1 %· 6 of 127 studies report it
  2. Workplace disorder / poor housekeepingWhole line or unspecified equipment1.0 %C0.3–2.4 %· 3 of 127 studies report it

Reduced speed

23 %of the lost time · 95% interval: 10–39 %
In the operations of this process
  1. Reduced speed operation of forming equipmentForming, moulding and depositing2.1 %C0.6–5.0 %· 4 of 76 studies report it
  2. Unspecified reduced-speed operation on packaging linePackaging (forming, sealing, wrapping, case packing, palletizing)1.6 %C0.5–3.6 %· 4 of 112 studies report it
  3. HFCS transfer pump flow below design capacityMixing and blending1.2 %D0.2–3.7 %· 1 of 31 studies reports it
  4. Fouled/dirty forming diesForming, moulding and depositing0.9 %D0.2–2.4 %· 1 of 76 studies reports it
In any line
  1. Reduced speed loss (cause not specified)Whole line or unspecified equipment1.2 %C0.3–2.8 %· 3 of 127 studies report it
  2. Station cycle time constraintWhole line or unspecified equipment0.7 %D0.1–1.8 %· 1 of 127 studies reports it
Quality

Process defects (scrap and rework)

10 %of the lost time · 95% interval: 5–17 %
In the operations of this process
  1. Unspecified packaging defectPackaging (forming, sealing, wrapping, case packing, palletizing)1.6 %B0.5–3.7 %· 5 of 112 studies report it
  2. Flexible package seal/forming defectPackaging (forming, sealing, wrapping, case packing, palletizing)1.3 %C0.4–3.0 %· 4 of 112 studies report it
  3. Baking process defects (under-proofed, burnt, contaminated product)Baking1.1 %C0.2–3.0 %· 2 of 60 studies report it
  4. Blow Molding Container DefectsForming, moulding and depositing1.0 %C0.2–2.7 %· 2 of 76 studies report it
In any line
  1. Unspecified process defectsWhole line or unspecified equipment1.7 %B0.6–3.7 %· 6 of 127 studies report it
  2. Rework of off-specification productWhole line or unspecified equipment1.5 %B0.5–3.4 %· 5 of 127 studies report it

Start-up losses (reduced yield)

2.9 %of the lost time · 95% interval: 1–7 %
In the operations of this process
  1. Product damage during restart after maintenancePackaging (forming, sealing, wrapping, case packing, palletizing)0.5 %D0.1–1.4 %· 1 of 112 studies reports it
In any line
  1. Product Loss in Transfer LinesWhole line or unspecified equipment0.9 %C0.2–2.1 %· 3 of 127 studies report it
  2. Product loss at start-up/shut-down due to line designWhole line or unspecified equipment0.5 %D0.1–1.3 %· 1 of 127 studies reports it

Other reported causes

Outside the six big losses: planned stops, organisational or external causes and losses the studies do not classify.
  1. Miscellaneous and unclassified lossesWhole line or unspecified equipment · Not classifiable from the report10 %A5.3–17 %· 29 of 127 studies report it
  2. Raw material shortage or nonconformanceWhole line or unspecified equipment · Organizational or external stops (material or personnel shortage, utilities outage)3.1 %A1.3–5.9 %· 10 of 127 studies report it
  3. Unspecified production stoppage (pelletizing/forming)Forming, moulding and depositing · Not classifiable from the report1.8 %C0.5–4.4 %· 4 of 76 studies report it
  4. Maintenance Program Downtime (Planned and Reactive)Whole line or unspecified equipment · Planned downtime (scheduled maintenance, breaks, no demand)1.6 %B0.5–3.6 %· 5 of 127 studies report it
  5. Waiting for Raw Material or Ingredient SupplyWhole line or unspecified equipment · Organizational or external stops (material or personnel shortage, utilities outage)1.5 %B0.5–3.5 %· 5 of 127 studies report it
  6. Unspecified packaging line lossPackaging (forming, sealing, wrapping, case packing, palletizing) · Not classifiable from the report1.4 %C0.4–3.2 %· 4 of 112 studies report it

The dot is the estimated probability and the band its 95% credible interval. All bars share one scale, from 0 to 20 %. The letter is the evidence grade: A is the strongest and D means the cause rests on one study or none.

Split of the lost time estimated from 18 studies of Bakery and pasta, Forming, baking and cooking.

2Chain of unit operations

6 of 7 operations have a published physical model. Select an operation for its full derivation.
  1. Mixing and blendingPhysical model
    Cycle or residence time
    Theoretical47.0 sTypical54.0 s
    Throughput
    Typical13.1 m³/h
    Energy per unit of product
    Theoretical0 kJ/kgTypical0.0104 kJ/kg
    Quality
    Theoretical0.984
    Yield
    Theoretical0.999952Typical0.9970
    Availability
    Theoretical0.9844Typical0.859
    Performance
    Theoretical1.00
    OEE
    Theoretical0.968
  2. Energy per unit of product
    Theoretical0 kJ/kg
    Quality
    Theoretical1.000000
    Yield
    Theoretical0.9942
    Availability
    Theoretical0.958
    Performance
    Theoretical1.00
    OEE
    Theoretical0.958
  3. FermentationEvidence synthesis only
  4. BakingPhysical model
    Energy per unit of product
    Theoretical0 kJ/kgBest documented396 kJ/kgTypical601 kJ/kg
    Yield
    Theoretical0.903
    Cycle or residence time
    Theoretical30.1 min
    Throughput
    Theoretical39.1 kg/m²/h
    Quality
    Theoretical1.00000
    Availability
    Theoretical0.917
    Performance
    Theoretical1.00
    OEE
    Theoretical0.917
  5. Energy per unit of product
    Theoretical32.2 kJ/kgBest available technique153 kJ/kgBest documented288 kJ/kgTypical1,363 kJ/kg
    Cycle or residence time
    Theoretical0.340 hBest available technique0.680 h
    Throughput
    Theoretical2.94 1/hBest available technique1.47 1/h
    Yield
    Theoretical0.9958
    Quality
    Theoretical0.9987
    Availability
    Theoretical0.863
    Performance
    Theoretical1.00
    OEE
    Theoretical0.862
  6. Energy per unit of product
    Theoretical6.57 × 10⁻⁶ kJ/kgBest available technique23.3 kJ/kgTypical39.5 kJ/kg
    Yield
    Theoretical1.00Best documented0.880
    Quality
    Theoretical0.9675Typical0.935
    Availability
    Theoretical0.938
    Performance
    Theoretical1.00
    OEE
    Theoretical0.907
  7. Cycle or residence time
    Theoretical0.00911 sTypical0.300 s
    Throughput
    Theoretical158 1/minTypical89.6 1/min
    Energy per unit of product
    Theoretical0 JTypical147 J
    Quality
    Theoretical1.00000
    Yield
    Theoretical0.9982
    Availability
    Theoretical1.00
    Performance
    Theoretical0.986
    OEE
    Theoretical0.986

3Line-level physics-bounded OEE

Bracket for the whole line from the modelled operations.
  • Upper value (ideal buffers)
    0.858 [0.809–0.901]
  • Lower value (no buffers)
    0.665 [0.593–0.720]

Based on 6 of 7 operations.

Upper value: ideal buffers and synchronised unavoidable stops (the line is bounded by its most constrained modelled operation). Lower value: no buffers and independent unavoidable stops (downtime ratios add, quality factors multiply, the slowest operation sets the rate). Operations without a physical model are not yet included, so both values are upper bounds for the whole line.

4Composition of lost time

Share of lost time among the six big losses for Bakery and pasta, Forming, baking and cooking.
Evidence gradeB18 studies, 19 units
  • Equipment failure (breakdowns)
  • Setup and adjustments
  • Idling and minor stops (micro-stops)
  • Reduced speed
  • Process defects (scrap and rework)
  • Start-up losses (reduced yield)
  • Equipment failure (breakdowns)Availability
    25% [13–38%]prediction 0–63%
  • Setup and adjustmentsAvailability
    19% [8–34%]prediction 0–83%
  • Idling and minor stops (micro-stops)Performance
    19% [8–33%]prediction 0–80%
  • Reduced speedPerformance
    23% [10–39%]prediction 0–86%
  • Process defects (scrap and rework)Quality
    10% [5–17%]prediction 0–34%
  • Start-up losses (reduced yield)Quality
    2.9% [0.7–7.3%]prediction 0.0–52.0%

Dots are posterior means; thick whiskers are 95% credible intervals; thin whiskers are 95% prediction intervals for a new line.

5Most probable causes

Probability of presence of each cause in food and beverage lines (all segments), highest first. The estimate by segment is on the page of each cause.

6Documented OEE

Pooled OEE and factors reported by the included studies of this group, and the best documented value.
MetricPooled estimate [95% CrI]Studies / unitsBest documented
OEE0.669 [0.613–0.723]21 / 361.00 · View study
Show verbatim quote
Based on the OEE calculation, the average value is 100%, indicating that the OEE meets world-class standards.
Availability0.843 [0.790–0.890]17 / 180.983 · View study
Show verbatim quote
November 98,30 87,40 97,44 83,70
Performance0.830 [0.777–0.875]16 / 210.984 · View study
Show verbatim quote
Disponibilidad (%) Desempeño (%) Calidad (%) OEE (%) Mejora (%) AS IS 78.32% 95.87% 95.94% 72.04% 13.03% TO BE 86.69% 98.39% 97.12% 82.84%
Quality0.929 [0.890–0.955]14 / 150.980 · View study
Show verbatim quote
quality of 98%, respectively

OEE documented in other processes of Bakery and pasta

Process familyOEEStudies / unitsEvidence grade
Filling and packaging line0.690 [0.638–0.752]6 / 6B
Thermal processing0.663 [0.560–0.747]0 / 0D
Mixing and formulation0.662 [0.528–0.753]1 / 1D
Milling, extraction and separation0.714 [0.646–0.802]1 / 1D
Whole plant or unspecified0.661 [0.588–0.723]1 / 3D