Thermal processing

Fluid (market) milk

Raw milk is clarified and standardized, homogenized, pasteurized, chilled, filled and packed.

In short

This is the line

Each station shows how far it can go according to physics. Select one to see its detail.

Out of every 100 hours planned for production
  1. 67produce

    Typical of the plants studied: the equivalent of 67 hours of good product at full speed (an OEE of 67 %).

  2. 19can be recovered

    The physics of this process allows up to 86 out of 100. This band is the possible improvement.

  3. 14are a physical limit

    No plant avoids them: mandatory cleaning and the minimum times needed to heat, cool or fill.

No included study measures this exact process: the typical value is that of all food and beverage lines (244 studies).

The most limiting station is Refrigeration and freezing: it reaches 86 % at most.

Where the time is lost

  • Breakdowns27 %

    The machine stops because something fails and has to be repaired.

  • Reduced speed24 %

    The line runs, but slower than it can.

  • Minor stops22 %

    Short stops the operator clears without maintenance: jams, waiting, blocked sensors.

  • Changeovers and adjustments19 %

    Time between one product and the next: format change, cleaning, warm-up and fine tuning.

  • Defects6 %

    Product that comes out wrong and is scrapped or reworked.

  • Start-up losses2 %

    Product lost while the line settles after starting.

Split for all food and beverage lines (195 studies); no study measures it for this exact process.

What most often stops lines like this one

Causes reported by the studies, from the most to the least frequent.

  1. Packaging machine breakdownappears in about 4 of every 100 lines studiedPackaging (forming, sealing, wrapping, case packing, palletizing) · Breakdowns · strong evidence
  2. Filler equipment breakdown (unspecified failure mode)appears in about 4 of every 100 lines studiedFilling · Breakdowns · strong evidence
  3. Filler changeover and adjustmentappears in about 4 of every 100 lines studiedFilling · Changeovers and adjustments · strong evidence
  4. Unspecified packaging defectappears in about 2 of every 100 lines studiedPackaging (forming, sealing, wrapping, case packing, palletizing) · Defects · good evidence
  5. Bearing failureappears in about 2 of every 100 lines studiedSeparation (centrifugation, filtration, membranes) · Breakdowns · limited evidence

See the technical detail

Technical detail

Uncertainty intervals, physical models per station and sources, for anyone who wants to check each figure.

1Why it stops: the six big losses

The most probable situations inside each loss, according to 429 published studies. The percentage estimates the probability that a food and beverage line shows that cause; the number of studies reporting it is given below.
Availability

Equipment failure (breakdowns)

27 %of the lost time · 95% interval: 17–39 %
In the operations of this process
  1. Packaging machine breakdownPackaging (forming, sealing, wrapping, case packing, palletizing)4.4 %A1.9–8.4 %· 12 of 112 studies report it
  2. Filler equipment breakdown (unspecified failure mode)Filling3.7 %A1.4–7.5 %· 12 of 120 studies report it
  3. Bearing failureSeparation (centrifugation, filtration, membranes)1.6 %C0.3–4.4 %· 2 of 37 studies report it
  4. Basic Condition and Operating Standard Non-CompliancePackaging (forming, sealing, wrapping, case packing, palletizing)1.1 %C0.3–2.7 %· 3 of 112 studies report it
In any line
  1. Unplanned equipment breakdownWhole line or unspecified equipment11 %A6.1–18 %· 30 of 127 studies report it
  2. Mechanical, electrical or pneumatic component failureWhole line or unspecified equipment1.4 %B0.5–3.2 %· 5 of 127 studies report it

Setup and adjustments

19 %of the lost time · 95% interval: 10–29 %
In the operations of this process
  1. Filler changeover and adjustmentFilling3.6 %A1.5–7.1 %· 11 of 120 studies report it
  2. Packaging Equipment Setup and AdjustmentPackaging (forming, sealing, wrapping, case packing, palletizing)1.0 %C0.3–2.5 %· 3 of 112 studies report it
  3. Packaging line changeoverPackaging (forming, sealing, wrapping, case packing, palletizing)1.0 %C0.3–2.3 %· 3 of 112 studies report it
  4. CIP (Clean-in-Place) cleaning cycleFilling0.9 %C0.2–2.2 %· 3 of 120 studies report it
In any line
  1. Changeover / setup timeWhole line or unspecified equipment11 %A5.6–17 %· 28 of 127 studies report it
  2. Cleaning and sanitation downtimeWhole line or unspecified equipment1.0 %C0.3–2.3 %· 3 of 127 studies report it
Performance

Idling and minor stops (micro-stops)

22 %of the lost time · 95% interval: 12–34 %
In the operations of this process
  1. Unspecified minor stoppage on filling lineFilling1.5 %B0.5–3.3 %· 5 of 120 studies report it
  2. Packaging/filling seal and handling mechanism faultPackaging (forming, sealing, wrapping, case packing, palletizing)0.8 %C0.2–2.0 %· 2 of 112 studies report it
  3. Palletizer minor stoppage (misalignment, jam or blockage)Packaging (forming, sealing, wrapping, case packing, palletizing)0.7 %C0.2–1.8 %· 2 of 112 studies report it
  4. Strapping machine malfunction / minor stoppagePackaging (forming, sealing, wrapping, case packing, palletizing)0.5 %D0.1–1.5 %· 1 of 112 studies reports it
In any line
  1. Idling and minor stoppagesWhole line or unspecified equipment1.9 %B0.6–4.1 %· 6 of 127 studies report it
  2. Workplace disorder / poor housekeepingWhole line or unspecified equipment1.0 %C0.3–2.4 %· 3 of 127 studies report it

Reduced speed

24 %of the lost time · 95% interval: 14–37 %
In the operations of this process
  1. Unspecified reduced-speed operation on packaging linePackaging (forming, sealing, wrapping, case packing, palletizing)1.6 %C0.5–3.6 %· 4 of 112 studies report it
  2. Separator running below rated throughputSeparation (centrifugation, filtration, membranes)1.2 %D0.2–3.9 %· 1 of 37 studies reports it
  3. Filler running below rated speedFilling1.1 %C0.3–2.7 %· 3 of 120 studies report it
  4. Operator-limited line speedPackaging (forming, sealing, wrapping, case packing, palletizing)0.7 %D0.1–1.8 %· 1 of 112 studies reports it
In any line
  1. Reduced speed loss (cause not specified)Whole line or unspecified equipment1.2 %C0.3–2.8 %· 3 of 127 studies report it
  2. Station cycle time constraintWhole line or unspecified equipment0.7 %D0.1–1.8 %· 1 of 127 studies reports it
Quality

Process defects (scrap and rework)

6.2 %of the lost time · 95% interval: 3–10 %
In the operations of this process
  1. Unspecified packaging defectPackaging (forming, sealing, wrapping, case packing, palletizing)1.6 %B0.5–3.7 %· 5 of 112 studies report it
  2. Filling process quality defectsFilling1.3 %B0.4–3.1 %· 5 of 120 studies report it
  3. Flexible package seal/forming defectPackaging (forming, sealing, wrapping, case packing, palletizing)1.3 %C0.4–3.0 %· 4 of 112 studies report it
  4. Off-spec liquid product from pasteurized base tankPasteurization1.0 %D0.2–3.4 %· 1 of 26 studies reports it
In any line
  1. Unspecified process defectsWhole line or unspecified equipment1.7 %B0.6–3.7 %· 6 of 127 studies report it
  2. Rework of off-specification productWhole line or unspecified equipment1.5 %B0.5–3.4 %· 5 of 127 studies report it

Start-up losses (reduced yield)

2.4 %of the lost time · 95% interval: 1–5 %
In the operations of this process
  1. Product damage during restart after maintenancePackaging (forming, sealing, wrapping, case packing, palletizing)0.5 %D0.1–1.4 %· 1 of 112 studies reports it
In any line
  1. Product Loss in Transfer LinesWhole line or unspecified equipment0.9 %C0.2–2.1 %· 3 of 127 studies report it
  2. Product loss at start-up/shut-down due to line designWhole line or unspecified equipment0.5 %D0.1–1.3 %· 1 of 127 studies reports it

Other reported causes

Outside the six big losses: planned stops, organisational or external causes and losses the studies do not classify.
  1. Miscellaneous and unclassified lossesWhole line or unspecified equipment · Not classifiable from the report10 %A5.3–17 %· 29 of 127 studies report it
  2. Raw material shortage or nonconformanceWhole line or unspecified equipment · Organizational or external stops (material or personnel shortage, utilities outage)3.1 %A1.3–5.9 %· 10 of 127 studies report it
  3. Maintenance Program Downtime (Planned and Reactive)Whole line or unspecified equipment · Planned downtime (scheduled maintenance, breaks, no demand)1.6 %B0.5–3.6 %· 5 of 127 studies report it
  4. Waiting for Raw Material or Ingredient SupplyWhole line or unspecified equipment · Organizational or external stops (material or personnel shortage, utilities outage)1.5 %B0.5–3.5 %· 5 of 127 studies report it
  5. Screw press downtime of mixed/unrecorded causeSeparation (centrifugation, filtration, membranes) · Not classifiable from the report1.5 %C0.3–4.2 %· 2 of 37 studies report it
  6. Unspecified filler loss (unclassified cause)Filling · Not classifiable from the report1.4 %B0.4–3.3 %· 5 of 120 studies report it

The dot is the estimated probability and the band its 95% credible interval. All bars share one scale, from 0 to 20 %. The letter is the evidence grade: A is the strongest and D means the cause rests on one study or none.

No included study reports the split of the lost time for Dairy products, Thermal processing; the percentages in the headers are those of all food and beverage lines (195 studies).

2Chain of unit operations

6 of 6 operations have a published physical model. Select an operation for its full derivation.
  1. Throughput
    Theoretical0.246 L/h/m²
    Energy per unit of product
    Theoretical5.55 × 10⁻¹¹ kJ/kg
    Yield
    Theoretical0.99990Typical0.9995
    Availability
    Theoretical0.9844
    Performance
    Theoretical0.929
    Quality
    Theoretical0.9987
    OEE
    Theoretical0.913
  2. HomogenizationPhysical model
    Energy per unit of product
    Theoretical0.00364 kJ/kgBest available technique10.5 kJ/kgBest documented14.6 kJ/kgTypical21.2 kJ/kg
    Yield
    Theoretical1.00
    Availability
    Theoretical0.9834
    Performance
    Theoretical1.00
    Quality
    Theoretical0.9987
    OEE
    Theoretical0.982
  3. PasteurizationPhysical model
    Energy per unit of product
    Theoretical0 kJ/kgBest available technique26.8 kJ/kgTypical80.4 kJ/kg
    Cycle or residence time
    Theoretical15.0 s
    Throughput
    Theoretical196 1/h
    Availability
    Theoretical0.9844Best documented0.958Typical0.850
    Yield
    Theoretical0.99992
    Quality
    Theoretical0.9986
    Performance
    Theoretical1.00
    OEE
    Theoretical0.983
  4. Energy per unit of product
    Theoretical32.2 kJ/kgBest available technique153 kJ/kgBest documented288 kJ/kgTypical1,363 kJ/kg
    Cycle or residence time
    Theoretical0.340 hBest available technique0.680 h
    Throughput
    Theoretical2.94 1/hBest available technique1.47 1/h
    Yield
    Theoretical0.9958
    Quality
    Theoretical0.9987
    Availability
    Theoretical0.863
    Performance
    Theoretical1.00
    OEE
    Theoretical0.862
  5. FillingPhysical model
    Yield
    Theoretical0.9949Best documented0.9948
    Quality
    Theoretical1.00
    Energy per unit of product
    Theoretical0.0419 kJ/kg
    Cycle or residence time
    Theoretical0.874 sTypical3.10 s
    Throughput
    Theoretical222,435 1/hTypical62,649 1/h
    Availability
    Theoretical0.995Typical0.972
    Performance
    Theoretical1.00
    OEE
    Theoretical0.995
  6. Cycle or residence time
    Theoretical0.00911 sTypical0.300 s
    Throughput
    Theoretical158 1/minTypical89.6 1/min
    Energy per unit of product
    Theoretical0 JTypical147 J
    Quality
    Theoretical1.00000
    Yield
    Theoretical0.9982
    Availability
    Theoretical1.00
    Performance
    Theoretical0.986
    OEE
    Theoretical0.986

Cross-cutting operations

Operations that serve the whole line and are not part of the product flow.

  • Cycle or residence time
    Theoretical22.5 minTypical90.0 min
    Other
    Theoretical0.00416 m³/tonne
    Energy per unit of product
    Theoretical0.00157 kJ/kgBest available technique0.477 kJ/kg
    Availability
    Theoretical0.953Typical0.842
    Quality
    Theoretical0.998
    OEE
    Theoretical0.951

3Line-level physics-bounded OEE

Bracket for the whole line from the modelled operations.
  • Upper value (ideal buffers)
    0.859 [0.811–0.907]
  • Lower value (no buffers)
    0.753 [0.690–0.813]

Based on 6 of 6 operations.

Upper value: ideal buffers and synchronised unavoidable stops (the line is bounded by its most constrained modelled operation). Lower value: no buffers and independent unavoidable stops (downtime ratios add, quality factors multiply, the slowest operation sets the rate). Operations without a physical model are not yet included, so both values are upper bounds for the whole line.

4Composition of lost time

Share of lost time among the six big losses for Dairy products, Thermal processing.
Evidence gradeD0 studies, 0 units
  • Equipment failure (breakdowns)
  • Setup and adjustments
  • Idling and minor stops (micro-stops)
  • Reduced speed
  • Process defects (scrap and rework)
  • Start-up losses (reduced yield)
  • Equipment failure (breakdowns)Availability
    31% [12–57%]prediction 0–76%
  • Setup and adjustmentsAvailability
    22% [6–47%]prediction 0–88%
  • Idling and minor stops (micro-stops)Performance
    21% [7–43%]prediction 0–83%
  • Reduced speedPerformance
    20% [6–41%]prediction 0–85%
  • Process defects (scrap and rework)Quality
    4.3% [1.2–9.4%]prediction 0.0–21.2%
  • Start-up losses (reduced yield)Quality
    1.7% [0.4–4.6%]prediction 0.0–41.5%

Dots are posterior means; thick whiskers are 95% credible intervals; thin whiskers are 95% prediction intervals for a new line.

5Most probable causes

Probability of presence of each cause in food and beverage lines (all segments), highest first. The estimate by segment is on the page of each cause.

6Documented OEE

Pooled OEE and factors reported by the included studies of this group, and the best documented value.

No included study reports the OEE of Dairy products, Thermal processing. The pooled estimate over all food and beverage lines is shown.

MetricPooled estimate [95% CrI]Studies / unitsBest documented
OEE0.666 [0.614–0.711]244 / 3791.00 · View study
Show verbatim quote
Based on the OEE calculation, the average value is 100%, indicating that the OEE meets world-class standards.
Availability0.844 [0.803–0.880]203 / 3641.00 · View study
Show verbatim quote
1.00 0.73 0.27 1.00 Lauterstar OEE Efficiency components
Performance0.820 [0.767–0.860]164 / 2871.00 · View study
Show verbatim quote
52.10% 99.95% 0,05% 0% 100% 99.37% 99.32%
Quality0.941 [0.912–0.959]154 / 2701.00 · View study
Show verbatim quote
Perhitungan nilai quality rate mesin washer tank bernilai 99,95%, mesin blancher bernilai 99,87%, mesin cooling bernilai 99,95%, mesin grading bernilai 99,97%, mesin sortasi belt bernilai 99,84%, mesin slicing bernilai 99,12%, mesin exhaust bernilai 100,00%, mesin seamer bernilai 99,80%, dan mesin retort bernilai

OEE documented in other processes of Dairy products

Process familyOEEStudies / unitsEvidence grade
Filling and packaging line0.692 [0.637–0.761]9 / 15B
Forming, baking and cooking0.671 [0.604–0.745]1 / 1D
Fermentation0.696 [0.601–0.814]1 / 1D
Slaughter, cutting and primary processing0.686 [0.613–0.771]1 / 1D
Whole plant or unspecified0.663 [0.588–0.738]4 / 4C